U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
Pine Ridge Reservation Landfill Fire - Removal Polrep



UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region VIII

Subject: POLREP #1
Removal Action Summary- Initial POLREP
Pine Ridge Reservation Landfill Fire
A809
Red Shirt, SD
Latitude: 43.5900000 Longitude: -102.8900000


To: Martin McComb, Emergency Response

From: Paul Peronard, OSC
Date: 6/14/2011
Reporting Period: 6/10/2011 to 6/14/2011

1. Introduction
  1.1 Background
   
Site Number: A809    Contract Number:  
D.O. Number:      Action Memo Date:  
Response Authority: CERCLA    Response Type: Emergency
Response Lead: EPA    Incident Category: Removal Action
NPL Status:    Operable Unit:
Mobilization Date: 6/12/2011    Start Date: 6/10/2011
Demob Date:      Completion Date:  
CERCLIS ID:    RCRIS ID:
ERNS No.:    State Notification:
FPN#:    Reimbursable Account #:


1.1.1 Incident Category

Other - Condemned Structure

1.1.2 Site Description

At approximately 17:00 on June 9, 2011, EPA Region 8 Emergency Response Program received a referral from EPA personnel working with the Oglala Sioux Tribe regarding a landfill fire on the Pine Ridge Reservation in South Dakota.  The phone duty EPA On-Scene Coordinator (OSC) contacted the local landfill manager, Tribal representatives and Indian Health Service (IHS) personnel.  Reports from the scene, including video and photographs, depicted a large, uncontrolled fire at the landfill’s main repository.  Local attempts to cover the area with soil were not successful and nearly resulted in a serious situation when a bulldozer operator and his equipment began sinking into the smoldering debris.  The local fire department responded to the fire but declined to become involved indicating that they did not have the proper equipment to fight the fire.  EPA OSC Paul Peronard deployed to the Pine Ridge Landfill Fire Site (Site) on June 12, 2011.

The Site is the sole landfill for the Pine Ridge Reservation and has been in operation for less than 10 years.  It is a Subtitle D solid waste facility that services some 11 transfer stations throughout the reservation.  The landfill supports approximately 30,000 people including the communities of Pine Ridge and Kyle.  Approximately 30-50 tons of municipal solid waste is deposited at the landfill on a daily basis.  Because there is no alternate facility and storage at the various transfer stations is limited, trash and potentially hazardous solid waste continues to be trucked into the landfill. 

1.1.2.1 Location

The landfill is located 13 miles south of Red Shirt along BIA Highway 41 in southwest South Dakota.  Approximate GPS coordinates are 43.590 north latitude and -102.890 west longitude.  The property is owned and operated by the Oglala Sioux Tribe and supported by the Federal Indian Health Service (IHS).

1.1.2.2 Description of Threat

The fire has progressed to include approximately 80 percent (~5 acres) of the landfill surface footprint.  As the wind shifts, a resulting noxious plume inundates nearby BIA Highway 41.  Initial measurements taken on June 13, 2011 indicate elevated levels of particulates, VOCs and carbon monoxide and decreased levels of oxygen.  Explosive pockets of gas are actively being released and both intact and exploded canisters (such as propane bottles used in household barbeques) have been observed.

Regular cover and compaction has not been applied consistently and the subsurface fire is expected to burn indefinitely, with the uncovered trash 10-12 feet deep providing fuel and furnace-type airflow throw the poorly compacted layers of waste.  Use of the landfill is largely unrestricted, and local contacts indicate that waste is not screened for hazardous household materials before it is deposited.

 As previously mentioned, there is no other facility capable of handling the reservation’s waste stream, even temporarily.  Thus, unless the fire is put out, landfill personnel as well as workers hauling daily loads to the landfill and motorists along BIA Highway 41 are at risk of exposure to a noxious plume of gases generated by the combustion of hazardous substances in the landfill.  In addition, if the landfill becomes unavailable due to the fire, waste will begin to back up throughout the reservation and public health will be impacted.

1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results

During his Preliminary Removal Assessment on June 12, 2011, OSC Peronard confirmed the conditions identified by the landfill operator and IHS.  Initial measurements of the smoke plume taken on June 13, 2011, indicate elevated levels of particulates, VOCs and carbon monoxide and diminished levels of oxygen.  Evidence of hazardous substances (pesticide containers, paint cans, small drums) is visibly evident throughout the fire’s footprint and nearby trash heaps are at risk of adding additional fuel to the fire.



2. Current Activities
  2.1 Operations Section
    .

2. Current Activities

 

2.1 Operations Section

 

 

2.1.1 Narrative

The emergency response actions discussed in this initial POLREP include the Preliminary Removal Assessment which occurred on Sunday, June 12, 2011, the Removal Site Evaluation which occurred on Monday, June 13, 2011, and the actual Removal/Response Action, which began on June 13, 2011.

2.1.2 Response Actions to Date

Sunday, June 12, 2011: Preliminary Removal Assessment

OSC Peronard went to the Site to assess the extent and threat posed by the landfill fire.  He found the Site completely unsecured and unmonitored and determined that approximately 80% or about 5 acres of the landfill were on fire.  He observed evidence of household hazardous waste throughout the burn zone and witnessed a noxious plume of smoke drifting across the nearby highway.  He determined that, due to the unconsolidated nature of the waste in the landfill and the advanced state at which the fire was burning, the fire would likely burn for months if not addressed.

Monday, June 13, 2011: Meeting with Oglala Sioux Tribe

OSC Peronard met with Hobert Yankton, the Director of Solid Waste for the
Oglala Sioux Tribe to discuss landfill operations and possible response actions.

 

Monday, June 13, 2011: Meeting with United States Indian Health Service (IHS)

OSC Peronard met with Anthony Kathol and Brent Rohlfs, the engineers with the IHS who helped design and construct the landfill.  OSC Peronard and these officials discussed the design of the existing facility, current plans for the future expansion of the landfill into a new cell and a location from which soil could be excavated in an effort to put out the fire.

Monday, June 13, 2011: Removal Site Evaluation and Scoping Meeting

OSC Peronard directed EPA's Superfund Technical Assessment and Response Team contactor to collect monitoring data on the plume and take GPS measurements to map both the landfill and the extent of the burned area.  He met with Emergency and Rapid Response Services (ERRS) contractors to discuss firefighting operations and response priorities. 

Monday, June 13, 2011: Initial Mobilization

An ERRS crew of five personnel arrived on Site in the late afternoon.  At this time, equipment began to arrive and the ERRS crew began work to stabilize the approach to the landfill on the northwest side of the landfill.  The ERRS crew also worked to cut a fire line in an attempt to halt the spread of the fire towards the northwest.

START continued to monitor the plume.


2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)

2.1.4 Progress Metrics

  • At this time, a firebreak has been constructed across the northwestern edge of the fire.
  • The fire is currently 0% contained.



  2.2 Planning Section
   

2.2 Planning Section

2.2.1 Anticipated Activities

2.2.1.1 Planned Response Activities

A borrow pit will be established south of the current landfill in an area that has been designated for future expansion.  Solid waste in the existing cell will be excavated, placed and compacted in appropriate lifts within the cell and then covered with borrow soil to smother the fire. 

2.2.1.2 Next Steps

None to report.

2.2.2 Issues

None to report.



  2.3 Logistics Section
   

2.3 Logistics Section

 

N/A



  2.4 Finance Section
   

2.4 Finance Section

2.4.1 Narrative

The costs below are estimated final figures for this response action based upon estimates and daily cost summaries that have been presented to EPA to date.  Accurate accounting of costs is expected to be presented in final invoices from ERRS and START contractors by the end of June 2011.

Estimated Costs *

 

 

Budgeted

Total To Date

Remaining

% Remaining

Extramural Costs

ERRS - Cleanup Contractor

<$400,000

$15,000

$385,000

96%

TAT/START

$20,000

$2,000

$18,000

90%

Intramural Costs

USEPA - Direct

$12,000

$1,000

$11,000

92%

 

Total Site Costs

$437,000

$0

$414,000

95%

* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.




  2.5 Safety Officer
   

2.5 Safety Officer

N/A



  2.6 Liaison Officer
   

2.6 Liaison Officer

N/A



  2.7 Information Officer
   

2.7 Information Officer

 

2.7.1 Public Information Officer

There is currently no media interest in this Site.

2.7.2 Community Involvement Coordinator

N/A



3. Participating Entities
  3.1 Unified Command
   

  

3. Participating Entities

 

3.1 Unified Command

 

 

N/A

 

 

 

 




  3.2 Cooperating and Assisting Agencies
   

3.2 Cooperating and Assisting Agencies

Oglala Sioux Tribe

Indian Health Service



4. Personnel On Site
 

4. Personnel On Site


Paul Peronard - U.S. Environmental Protection Agency On-Scene-Coordinator
Martin McComb - U.S. Environmental Protection Agency On-Scene Coordinator

Russ  Nelson- Superfund Technical Assessment and Response Team Contractor, Technical Specialist

Terry Henderson - Emergency and Rapid Response Services Contractor, Removal Manager/Foreman
Steve Harrington – ERRS Contractor, Equipment Operator
Kory Martin – ERRS Contractor, Equipment Operator
Joseph Cordova – ERRS Contractor, Equipment Operator



5. Definition of Terms
  5. Definition of Terms

6. Additional sources of information
  6.1 Internet location of additional information/reports
    6. Additional sources of information

6.1 Internet location of additional information/reports

To be established COB June 14, 2011 as internet connectivity permits.



  6.2 Reporting Schedule
    6.2 Reporting Schedule

7. Situational Reference Materials
  7. Situational Reference Materials