Activities conducted during this reporting period:
Following arrival to the Site at 1130 hrs, the FOSC and START integrated into the Unified Command (UC). The UC included representatives from the Gordon County Fre Department (GCFD), Gordon County Emergency Management Agency (GCEMA), Georgia Environmental Protection Division (GEPD), Georgia Department of Natural resources (GDNR) and Georgia Department of Safety and Transportation (GDOT).
As of 2200 hrs, the responsible party, Transportation Services Unlimited (TSU) contractor, Marion Environmental inc (MEI), completed the transfer of NaOH from the tank and removal of of the wreckage from the Site. The transport manifest indicated the tank was carrying 3,900 gallons 50% solution NaOH. Based on the amount remaining in tank, TSU estimates 2,577 gallons released to the roadside ravine and directly into a tributary of Lick Creek. Reconnaissance of the area indicated elevated pH along a 1/2 mile stretch of the tributary. There was no evidence observed during the reconnaissance which indicated an impact to downstream Salacoa Creek.
An underflow dam was constructed 1/2 mile southwest and downstream of the head water/spill point of entry(POE). The elevated pH product and water is being removed from the tributary via vacuum trucks and either transported directly to the TSU facility or transferred to onsite frac tanks for temporary storage and future transport.
To date, an estimated 38,000 gallons of elevated pH water has been recovered from the waterway and transported offsite for recycling at the nearby TSU facility. The pH of the creek ranges from 13 (at POE) to 10.0 (recovery station).
Currently, pumping operations are being conducted simultaneously at the POE and downstream recovery station. A secondary recovery station downstream of the makeshift dam is planned as a precautionary measure to catch any overflow. Downstream intakes have been identified and are being monitored. The Calhoun County water treatment plant, located approximately 2 miles downstream of the Site was notified of the incident, and the facility indicated it would be able to handle the elevated pH, if impacted. No indication of such an impact is evidenced at this time. The release appears to be confined to the immediate area within 1/2 mile of the POE.
A 24 hour operational period has been established. TSU has engaged the necessary resources to mitigate the release and conduct cleanup operations. GEPD is providing oversight but has requested technical support from EPA. EPA will continue to monitor the situation and assist, as necessary.
ONSCENE PERSONNEL:
INCIDENT COMMAND GCFD (1) GDOT (1) GEPD (1) EPA (1) COMMAND AND GENERAL STAFF GCEMA (4) GEPD (1) GDNR (1) TSU RP (1) FIELD OPERATIONS GCFD Hazmat(6) MEI(11) Law Enforcement (2) START (2)
|