POLLUTION REPORT
|
| Date: |
Friday, February 20, 2009
|
| From: |
Stavros Emmanouil/Craig Thomas
|
| To: |
Craig Thomas, USEPA/ERB/RS III
|
Stavros Emmanouil, U.S. EPA/ERB/RS III
|
|
Jason El-Zein, U.S. EPA, ERB 1
|
David Chung, U.S. EPA
|
|
Melinda Dejewskie, City of St. Francis
|
Andrew Boettcher, Wisconsin DNR
|
|
Franklin Lockwood, City of St. Francis
|
Nola Hicks, U.S. EPA
|
|
John Maritote, U.S. EPA
|
Bill Ryczek, U.S. EPA
|
|
Roxanne Chronert, WDNR
|
Linda Nachowicz, U.S. EPA
|
|
Charles Gebien, ERB/RS III
|
|
|
Subject:
|
Continuation of Removal Action
St. Francis Auto Wreckers
4043 South Pennsylvania Avenue,
St. Francis, WI
Latitude: 45.9714000 Longitude: -87.8800000
|
| POLREP No.: |
13
|
Site #:
|
B5LD
|
| Reporting Period: |
2/16/2009 thru 2/20/2009
|
D.O. #:
|
0015
|
| Start Date: |
10/20/2008
|
Response Authority:
|
CERCLA
|
Mob Date: |
10/20/2008
|
Response Type:
|
Time-Critical
|
| Demob Date: |
|
NPL Status:
|
Non NPL
|
| Completion Date: |
|
Incident Category:
|
Removal Action
|
| CERCLIS ID #: |
WID988639068
|
Contract #
|
EP-S5-08-02
|
| RCRIS ID #: |
|
|
|
Continued the air monitoring of both the perimeter and the work area.
Transported and disposed of approximately 450 tons of PCB-contaminated soils (approximately 2925 total tons).
Received draft analytical results for samples collected from test pits excavated in the access roads along the east and north site boundaries. Draft results indicated that the soils beneath the access roads are not hazardous.
Received draft analytical results for samples collected from the stockpiled soils from the site. Draft results indicated that no further treatment for lead is required.
Secured the site and de-mobilized pending final excavation-area test pit sample results and conclusion of Regional On-Scene Coordinator training.
|
|
Continue sampling soil stockpile & generate waste profiles.
Excavate/Treat Impacted Soils, as necessary.
Transport/Dispose Drums & Impacted Soils.
Backfill & Grade Excavated Areas.
Restore Site, as necessary.
|
|
Transport and dispose of treated soils, and untreated PCB-contaminated soils.
Await final test pit sample results collected in roads along the east and north boundaries of the excavation-area.
Continue the excavation of contaminated soils and buried drums to four feet below the surface, pending final excavation-area test pit sample results.
Continue the air monitoring and waste characterization sampling activities.
Continue the treatment of mixed PCB waste, pending final test pit and stockpiled soil sampling results.
|
|
Secure funding for the continuation and completion of the project.
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| ERRS - Cleanup Contractor |
$992,963.00 |
$913,652.19 |
$79,310.81 |
7.99% |
| RST/START |
$79,420.00 |
$68,537.83 |
$10,882.17 |
13.70% |
|
Intramural Costs
|
| |
| Total Site Costs |
$1,072,383.00 |
$982,190.02 |
$90,192.98 |
8.41% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
| Waste Stream |
Quantity |
Manifest # |
Disposal Facility |
| PCB Contaminated Soils |
2925 |
000193530VES thru 000193538VES; 004659708JJK thru 004659710JJK; 004659934JJK thru 004659942JJK |
Wayne Disposal Belleville, MI |
response.epa.gov/stfrancisautowreckers
POLREP #13 Last Updated 2/20/2009
|