U.S. EPA OSC Steve Faryan and Weston Solutions Inc. (WSI) START personal, Ben Maradkel commence oversight, while PRP contractor installs soil vapor extraction (SVE) wells. On 30 October 2002 PRP contractors completed delineating the subsurface contamination. A total of seven hundred and nineteen samples were collected by the PRP contractors and U.S. EPA contractor collected ten percent split samples. Once data was validated, reviewed and tabulated, remediation area was determined. U.S. EPA, Illinois EPA, Village of Lisle and PRP meet once a week to discuss site activities and schedule.
■ Completed delineating the subsurface contamination.
■ Constructed the temporary parking lot.
■ Graded the remediation area and constructed the plenum.
■ Installed catch basin for plenum runoff water.
■ Constructed haul road south of the Lockformer plant.
■ Installed chain link fence and silt fence.
■ Transported and Disposed decontamination and well water off-site.
■ Installation of soil vapor extraction (SVE) wells.
|