United States Environmental Protection Agency
Region V
POLLUTION REPORT



Date:
Monday, December 30, 2002
From:
Steven Faryan


Subject: 

Lockformer
711 Ogden Avenue, Lisle, IL
Latitude: 41.8017000
Longitude: -88.0625000


POLREP No.:
4
Site #:
B5Y5
Reporting Period:
21 December 2002 to 30 December 2002
D.O. #:
Start Date:
 
Response Authority:
CERCLA
Mob Date:
7/22/2002
Response Type:
Demob Date:
 
NPL Status:
Completion Date:
 
Incident Category:
Removal Assessment
CERCLIS ID #:
Contract #
RCRIS ID #:
 

Site Description

See Site Profile Page


Current Activities

U.S. EPA OSC Steve Faryan and Weston Solutions Inc. (WSI) START personal, Ben Maradkel continue conducting oversight, while PRP contractor installs soil vapor extraction (SVE) wells.

■ Installation of eleven soil vapor extraction (SVE) wells.

■ Reinforced haul road south of the Lockformer plant with more gravel to reduce tracking of mud on to the streets.

■ Transported and Disposed soil cuttings off-site.

■ Cut concrete inside the plant (west portion) to install SVE wells and electrodes.


Planned Removal Actions

■ PRP will remediate the surficial silty clay till and fill in Area 1 and 2 with Electrical Resistive Heating (ERH) technology.

■ PRP will remediate the mass waste sand and gravel in Area 1 and 2 with SVE technology.


Next Steps

■ Continue to install SVE wells.

■ Solve run-off problem in temporary parking lot (TBD e.g. catch basin)

■ Cut into concrete floor inside plant (former degreaser area).

■ Install equipment and process piping to the SVE wells.

■ Construct storage building.

■ Install electrodes and vapor wells for ERH.

■ Hookup vapor/air/water piping (ERH).

■ Review and Approve confirmation sampling plan.

■ Transport and Dispose soil cuttings and decontamination water off-site.


Estimated Costs *
  Budgeted Total To Date Remaining % Remaining
Extramural Costs
RST/START $275,100.00 $173,000.00 $102,100.00 37.11%
Intramural Costs
 
Total Site Costs $275,100.00 $173,000.00 $102,100.00 37.11%

* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.


response.epa.gov/lockformer

POLREP #4 Last Updated 3/3/2004