• Since September 2003, OSC Allen Jarrell assisted OSC Tsang in coordinating field activities including conducting oversight of the permanganate sampling, attending meetings and participating in conference calls for the site.
• From October 17, 2003 to November 13, 2003, Weston-Manchester developed construction plans for the installation of a sheetpile dam with stop log to replace the existing temporary sand bag dam.
• On October 21, 2003, EPA/START conducted a comprehensive permanganate monitoring sampling of all 99 injection wells and selected monitoring wells. The sodium permanganate concentration continues to persist in most of the down gradient injection points at an average concentration of approximately 2%. Groundwater elevation data was also collected for all the injection point well locations. • From November 3 to December 2, 2003, Atlantic Retek, subcontractors to property owner Central Massachusetts Economic Development Authority, removed oil-contaminated debris from canal sluiceway north of Route 122A (Main Street) along the former mill building foundation and performed on-site asphalt batching treatment of the oil-contaminated soil pile located west of the canal sluiceway. The treated asphalt batch soil is being temporarily stored on-site. • On November 13, 2003, EPA/ERRS conducted a bid walk for the construction and installation of a sheet and stop log dam to replace the existing temporary sand bag dam. Bid walk attendees included representatives from EPA/START, Weston-Manchester, South Grafton Water District, MA DEP, Cyn Environmental, and Carter Pile. • On November 17 and 18, 2003, EPA/START collected VOC samples from 45 injection well and monitoring well locations where permanganate concentrations were below 1% (visually clear) and one surface water location from the Blackstone Canal. Samples were field screened on-site by the EPA New England Regional Laboratory (NERL) Mobile Laboratory and additional samples were sent back to NERL in Chelmsford for confirmatory analysis. Groundwater elevation data was also collected for all the injection point well locations.
• From December 4 to 23, 2003, EPA/ERRS subcontractors constructed and installed the sheet piled dam with stop log to replace the existing temporary sand bag dam.
• On December 12, 2003, MA DEP subcontractor installed 8 additional steel drivepoint injection wells (IP-116 to IP-123) in a line extending eastward from the IP-15 location.
• On December 16, 2003, groundwater samples were collected from each of the steel drivepoint wells and taken to NERL for VOC analysis. Preliminary results of the VOC analysis of the screening samples provided by NERL:
* The concentration of PCE ranged from 1 ppb to 1.9 ppb. * The concentration of TCE ranged from non-detect (ND) to 84 ppb. * The concentration of cis-DCE ranged from ND to 198 ppb.
• On December 17 and 18, 2003, Shaw injected 1 55-gallon drum of 40% solution into the following injection well locations: IP-6, IP-7, IP-11, IP-12, IP-16, IP-21, IP-57, IP-63, IP-67, IP-116, IP-117, IP-118, IP-119, IP-120, IP-122, and IP-123. Injection into IP-121 was not attempted since the steel riser was bent approximately 10 feet below ground surface causing unknown damage to joints and screen. Injection into IP-62 was stopped soon after starting due to leaking from the PVC riser joint just below the ground surface. These injection locations were moved to IP-11 and IP-21.
• From December 18 to 23, 2003, Shaw conducted 24-hour groundwater re-circulation of the injection grid area. Groundwater was pumped from injection wells IP-99, IP-55, and IP-89 into IP-116 to IP-120, IP-122, and IP-123. Approximately 5,000 gallons of groundwater was re-circulated into IP-116, IP-117, IP-118, IP-119, and IP-123 (~5,500 gallons). Approximately 7,000 gallons was re-circulated into IP-120 and IP-122 (~6,900). Approximately 7,000 gallons of groundwater was re-circulated/pumped from MW-104 and injected into IP-7. Permanganate concentrations of groundwater re-circulated from IP-99, IP-55, IP-89, and MW-104 was approximately 1-2% permanganate.
• As of December 27, 2003, personnel and equipment/supplies including the office trailer, dumpster, port-a-johns, and equipment storage connex box were demobilized from the site.
|