POLLUTION REPORT
|
| Date: |
Thursday, April 16, 2009
|
| From: |
Greg Fife
|
| To: |
Debbie Dietrich, Office of Emergency Management
|
Ragan Broyles, EPA
|
|
Subject:
|
Final PolRep
Many Diversified Interests
3617 Baer Street,
Houston, TX
Latitude: 29.7679250 Longitude: -95.3297000
|
| POLREP No.: |
20
|
Site #:
|
06FE
|
| Reporting Period: |
03/24-04/02/2009
|
D.O. #:
|
|
| Start Date: |
3/24/2009
|
Response Authority:
|
CERCLA
|
Mob Date: |
3/24/2009
|
Response Type:
|
Time-Critical
|
| Demob Date: |
4/2/2009
|
NPL Status:
|
NPL
|
| Completion Date: |
4/2/2009
|
Incident Category:
|
Removal Action
|
| CERCLIS ID #: |
TX0002288082
|
Contract #
|
|
| RCRIS ID #: |
|
|
|
The Site is a large residential area surrounding the former forge facility. Soil was contaminated with lead and other heavy metals believed to be from the facility. The majority of the off-site work has been conducted in years past. However, persistent discussions with two land owners eventually resulted in acquiring site assess on six parcels of land. Those parcels has lead contamination about the action level.
|
|
The yards were excavated. The contaminated soild disposed of offsite. The yards were backfilled and restored.
|
|
No future removal action is anticipated.
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
|
Intramural Costs
|
| |
| Total Site Costs |
$0.00 |
$0.00 |
$0.00 |
0.00% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.