Excavation and removal of all remaining municipal waste from the cell 5/7 isolation break was completed on April 17, 2009. Approximately 373,000 cubic yards of waste was relocated to cells 7 and 8a during the project.
During the current reporting period, Republic contractors installed leachate and landfill gas extraction systems and sections of flexible membrane liner (FML) temporary cap within the isolation break. In addition, work commenced on the following augmentations to the gas extraction system: installation of 11 proposed replacement wells and one new well in the 88-acre remediation area; replacement of 12 existing wells in cell 7 and 8a that were extended as waste from the isolation break was gradually filled and graded into cell 7, and 8 new proposed wells to be installed in cells 5 and 7 along the slopes of the isolation break. Daily progress on these tasks is annotated below.
From April 4, 2009, through April 6, 2009, remediation operations were suspended due to heavy rain.
From April 7, 2009, through April 9, 2009, Republic contractors began installation of a toe drain in the isolation break. The toe drain was installed immediately south of the 5/7 berm in cells 5b and 5c, and was connected to the sump at the western side of the isolation break with a 2% grade falling westward.
On April 8, 2009, Republic contractors decommissioned relief well RW-4 in cell 5a. Since its installation in February, 2008, RW-4 had gradually been affected by localized settlement trends that eventually rendered the well ineffective and unrepairable. Formal decommissioning reports for both RW-3(see POLREP #9) and RW-4 were submitted to Ohio EPA by Republic.
On April 10, 2009, remediation operations were suspended due to rain.
From April 13, 2009, through April 14, 2009, Republic contractors continued to install the toe drain in the isolation break. On April 14, 2009, a bucket auger drill rig was mobilized to cell 7 to begin drilling scheduled gas extraction wells in cell 7. Proposed gas extraction replacement well PW-301R(2) was installed. At 1200 on April 14, 2009, remediation operations were suspended due to heavy rainfall.
On April 15, 2009, remediation operations were suspended due to rain.
From April 16, 2009, through April 17, 2009, Republic contractors continued to install the toe drain in the isolation break. Proposed gas extraction well replacements PW-308R(2), PW-309R(2) and PW-341R were installed in cell 7. The drill rig was demobilized from cell 7 for regular maintenance.
From April 20, 2009, through April 21, 2009, remediation operations were suspended due to rain.
On April 22, 2009, replacement gas extraction well PW-134R was installed in cell 6a.
On April 23, 2009, replacement gas extraction well PW-133R was installed in cell 6a, and PW-158R was installed in cell 5d. Weather conditions precluded work from proceeding in the 5/7 isolation break.
On April 24, 2009, replacement gas extraction well PW-141R was installed in cell 5a, and PW-188R was installed in cell 4b. A shallow anchor trench was excavated mid-slope in cell 7 in the isolation break and a liner crew began installing and welding sections of FML temporary cap to the basal liner on the north side of the 5/7 berm.
On April 25, 2009, shallow anchor trenches were excavated mid-slope in cell 5 of the isolation break and the liner crew began installation and welding of FML temporary cap to the basal liner on the south side of the 5/7 berm.
On April 27, 2009, replacement gas extraction well Q1R was installed in cell 4a, and well W1R(2) was installed in cell 4b. The liner crew continued installation and welding of FML temporary cap to the basal liner on the south side of the 5/7 berm.
|