United States Environmental Protection Agency
Region V
POLLUTION REPORT



Date:
Tuesday, May 12, 2009
From:
Brian Kelly

To:
Brian Kelly, Superfund - ERB
Linda M. Nachowicz, U.S. EPA
Jason El-Zein, U.S. EPA
Mark Durno, EPA
David Chung, U.S. EPA - HQ
Beverly Kush, U.S. EPA
Barbara Carr, U.S. EPA
Michael Browning, START
Carol Ropski, U.S. EPA
Maryjane Adamo, U.S. EPA
Tracy Johnson, U.S. EPA
Patrick Hamblin, U.S. EPA
John Maritote, U.S. EPA
Brian Schlieger, U.S. EPA
Mick Hans, U.S. EPA
Michael Chezik, U.S. DOI
Jane Mackey, Congressman Conyers
Jeffrey Bonkoski, Trenton FD
Dave Michalak, Trenton FD
Joe Walczak, MDEQ
Paul Owens, MDEQ
Dan Yordanich, MDEQ
Richard Conforti, MDEQ
Edward Novak, MDEQ
Tracy Kecskemeti, MDEQ
Erin Irwin, Wayne County
Mark Hammond, Wayne County
Susan Thompson, Wayne County
Mayor Gerald R. Brown, City of Trenton
Raymond Wojtowicz, Wayne County
Randy Schoen, City of Trenton
Jack Ghannam, Wayne County
Bob Burns, Detroit River Riverkeeper
FEMA Watch, FEMA

Subject: 

Initiation of Fund-Lead Removal
DSC Trenton
1491 W Jefferson, Trenton, MI
Latitude: 42.1636000
Longitude: -83.1703000


POLREP No.:
3
Site #:
B5KV
Reporting Period:
D.O. #:
Start Date:
5/12/2009
Response Authority:
CERCLA
Mob Date:
5/12/2009
Response Type:
Time-Critical
Demob Date:
 
NPL Status:
Non NPL
Completion Date:
 
Incident Category:
Removal Action
CERCLIS ID #:
Contract #
RCRIS ID #:
 

Site Description

The DSC-Trenton Site (aka Detroit Steel Co formerly McLouth Steel) is a former steel production facility located at 1491 West Jefferson Avenue, Trenton, Michigan.

On January 31, 2008, DSC completed the voluntary removal of 1,091 containers of waste; however, attempts by EPA to enter into an administrative order on consent with DSC for the removal of PCB transformers and 3,700 PCB capacitors were unsuccessful and on September 2, 2008 EPA issued a unilateral administrative order (V-W-08-C-909).

On October 3, 2008, DSC agreed to comply with the UAO, and a work plan (Work Plan for Removal of PCB Equipment and Related Materials) was submitted to and approved by EPA that included the progressive removal of PCB containing equipment.

On March 2, 2009, EPA issued a failure to comply letter to DSC for failing to comply with the removal schedule. On March 26, 2009, DSC informed EPA that funding was unavailable to complete the removal work.


Current Activities

On May 12, 2009, EPA mobilized to the site to perform a hazard analysis of each transformer location and the capacitor mezzanine.


Planned Removal Actions

1) During the week of May 18, EPA will sample each of the transformers for disposal,
2) Pending sample results, no work will occur on site during the weeks of May 25 or June 1,
3) Beginning the week of June 8, EPA will drain the transformers and arrange for disposal,
4) Following removal of transformer oils, EPA will begin disposal of capacitors.


Next Steps

Finalize work plan and health and safety plan.


Estimated Costs *
  Budgeted Total To Date Remaining % Remaining
Extramural Costs
ERRS - Cleanup Contractor $300,000.00 $5,000.00 $295,000.00 98.33%
START $25,000.00 $1,000.00 $24,000.00 96.00%
Intramural Costs
 
Total Site Costs $325,000.00 $6,000.00 $319,000.00 98.15%

* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.


response.epa.gov/dsctrenton

POLREP #3 Last Updated 5/20/2009