Friday, June 5, 2009, installation of demarcation layer continues in locations where 1 foot of soil has been removed and backfilling with clean fill continues. Installation of turf matting and rock toe and application of hydroseed continues along shoreline.
June 6 through June 10, no site activities were conducted and site security monitored the site. No activities from June 8 through June 10 were conducted due to rain.
Thursday, June 11, 2009, Installation of landscaping stone began at Property A (ECA locations 01 and 02).
Friday, June 12, 2009, installation of landscaping stone for barrier continues at ECA-02 and barrier is installed at ECA-06. Demarcation and backfilling activities continue at WMP.
Saturday, June 13, 2009, landscaping activities continue at ECA-02.
Sunday, June 14, 2009, no site activities were conducted and site security monitored the site.
Monday, June 15, 2009, Barrier installation at ECA-02 complete. Demarcation, backfilling, and shoreline activities resume at WMP.
Tuesday, June 16, 2009, soil excavation and hauling activities resume along remaining 20% of WMP. Landscaping and hydroseeding begins within northwest section of WMP that has been backfilled and graded. Demarcation, backfilling, and shoreline activities continue.
June 17 through June 18 2009, no site activities conducted due to rain.
During the reporting period, 1,708 tons of contaminated soils have been transported to the disposal facility.
Security continues to keep trespassers from entering the park during non-working hours.
|