United States Environmental Protection Agency
Region IV
POLLUTION REPORT



Date:
Thursday, June 25, 2009
From:
Leslie Sims, FOSC

To:
James Webster, USEPA R4 ERRPB

Subject: 

Initiation of Removal Action (Enforcement-Lead)
ESB
1246 Allene Avenue and Neighboring Properties, Atlanta, GA
Latitude: 33.7167000
Longitude: -84.4008000


POLREP No.:
10
Site #:
A4AB
Reporting Period:
D.O. #:
0045
Start Date:
2/15/2006
Response Authority:
CERCLA
Mob Date:
2/15/2006
Response Type:
Time-Critical
Demob Date:
6/25/2009
NPL Status:
Non NPL
Completion Date:
 
Incident Category:
Removal Action
CERCLIS ID #:
GAD078105749
Contract #
68-S4-02-04
RCRIS ID #:
 

Site Description

The ESB, Inc., Site (Site), located at 1246 Allene Street in Atlanta, Fulton County, Georgia, is a defunct manufacturing facility which produced lead-acid automobile batteries from 1948 to 1988.  Facility operations included casting lead alloys, producing oxides of lead, mixing lead pastes, and forming positive and negative battery plates.  Manufacturing operations ceased in 1988.  The Site, situated on 12 acres of land in a mixed-use zoning area in southwest Atlanta, Georgia is bordered by a railroad spur on the north, and residential properties on the west, southeast and south. The nearest residential property is located approximately 500 feet to the west of the facility.  A child care center is located directly across the street from the facility to the west.  It was alleged that during the manufacturing process, lead particles were released to the atmosphere via emissions from elevated roof stacks at the facility and impacted some of the surrounding properties.  

In accordance with the AOC, EPA conducted a fund-lead, time-critical removal action at residential and commercial properties located in the immediate outside perimeter of the ESB facility. This cleanup action included the remediation of lead and arsenic from 48 residential yards and a ditch located downgradient and due north of the facility.  Prior to remediation, lead contaminated soils in the yards and ditch revealed elevated lead of 500 mg/kg and 44,000 mg/kg, respectively.

An EPA Fund-lead, Time-Critical Removal Action was implemented at the Site to mitigate lead-contaminated soils identified at residential and commercial properties located in the immediate vicinity of the ESB facility. Lead contamination identified at the properties remediated during this action are suspected to have been directly impacted as a result of historical operations at the ESB facility.

Exide Technologies remains responsible for the cleanup at the ESB facility property which is scheduled to begin in Fall 2009.



Current Activities

Activities conducted during this reporting period:


Planned Removal Actions

Asbestos abatement and demolition of the boiler house.


Key Issues

Oversight collaboration with GEPD


Estimated Costs *
  Budgeted Total To Date Remaining % Remaining
Extramural Costs
RST/START - Tetra Tech $10,000.00 $0.00 $10,000.00 100.00%
Intramural Costs
 
Total Site Costs $10,000.00 $0.00 $10,000.00 100.00%

* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.


response.epa.gov/ESB

POLREP #10 Last Updated 1/7/2013