|
United
States Environmental Protection Agency
Region IV
POLLUTION REPORT
|
| Date: |
Monday, June 29, 2009
|
| From: |
Leonardo Ceron
|
| To: |
James Webster, Oil and Removal Program Section, ERRB, EPA
|
Jim Mcguire, Removal Program, ERRB, Superfund
|
|
Christopher Masterson, USEPA R4 ERRB
|
|
|
Subject:
|
Excavations Continues
Goodyear Dump Site
556 Buffalo Hollow,
Berea, KY
Latitude: 37.5272000 Longitude: -84.3367000
|
| POLREP No.: |
3
|
Site #:
|
A4LP
|
| Reporting Period: |
|
D.O. #:
|
|
| Start Date: |
6/23/2009
|
Response Authority:
|
CERCLA
|
Mob Date: |
6/22/2009
|
Response Type:
|
Time-Critical
|
| Demob Date: |
|
NPL Status:
|
Non NPL
|
| Completion Date: |
|
Incident Category:
|
Removal Action
|
| CERCLIS ID #: |
KYN000409853
|
Contract #
|
|
| RCRIS ID #: |
|
|
|
Site excavation continues. The following grids which contained contaminated soils have been excavated: D-2, G-7,I-11,J-11,H-12,G-14. Initial analytical results for grids D-2, J-11 have confirmed the removal of contaminated soils and are cleared for back fill. Grid I-11 results indicated additional excavation was warrented. Analytical results from grids G-7,I-11,H-12,and G-14, will be available by COB 07-10-09.
Two of three contaminated soils stock piles have been completed and are awaiting disposal based on analytical profiles.
Back fill operations have begun in grid D-2, stockpiling of clean fill will continue.
|
|
Excavation of contaminated soils is expected to continue through the week of July 13th. Stockpiles of clean fill is expected to continue through the week of July 10th. Upon receipt of analytical results from contaminated stockpiles, disposal will begin and is expected to last at least two weeks.
The relocation of one resident on Site is expected to occur during the week of July 7th for one week. Relocation is necessary, as grid F-3 is located in resident’s septic drainage field. During excavation all water and sewage flow will be stopped for approximately 5 days, as soil excavation and backfill is conducted. The excavation of this grid may also require the replacement of the septic drainage lines from this residential property.
|
|
Excavation and analytical results from all grids is expected to be completed by the week of July 10th. Analytical Results from the contaminated stock for disposal purposes is expected to be completed by the week of July 13th. Disposal is expected to begin the week of July 13th.
|
|
KDEP continues to provide a presence on Site during the removal process. EPA will cooperate with KDEP on additional removal of suspect soil contamination areas and drainage sediment soil areas, as long as current removal funds for Site allow.
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| ERRS - Cleanup Contractor |
$310,000.00 |
$151,900.00 |
$158,100.00 |
51.00% |
| RST/START |
$30,000.00 |
$11,436.00 |
$18,564.00 |
61.88% |
|
Intramural Costs
|
| |
| Total Site Costs |
$340,000.00 |
$163,336.00 |
$176,664.00 |
51.96% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
response.epa.gov/goodyeardump
POLREP #3 Last Updated 10/6/2009
|