United States Environmental Protection Agency
Region VI
POLLUTION REPORT



Date:
Tuesday, July 7, 2009
From:
Adam Adams

To:
Peter Ricca, LDEQ
Debbie Dietrich, EPA

Subject: 

Continuation of LDEQ Removal Action
Kriger Battery
7179 Adams Lane, Greenwood, LA
Latitude: 32.4374800
Longitude: -93.9434900


POLREP No.:
11
Site #:
06TH
Reporting Period:
06/21/2007 - 06/27/2009
D.O. #:
Start Date:
4/14/2009
Response Authority:
CERCLA
Mob Date:
4/13/2009
Response Type:
Time-Critical
Demob Date:
 
NPL Status:
Non NPL
Completion Date:
 
Incident Category:
Removal Action
CERCLIS ID #:
LA0000605270
Contract #
EP-W-06-042
RCRIS ID #:
 

Site Description

The Kriger Battery removal site is located in Greenwood, Caddo Parish, Louisiana on commercial/industrial zoned property.  The site is a former battery reclamation facility that operated between 1972 and 1982 and consisted of a processing building, acid neutralization pit, and hammer mill area.  Historical sampling conducted by the Louisiana Department of Environmental Quality (LDEQ)shows on-site lead concentrations as high as 112,660 mg/kg.  Elevated lead concentrations have been located off-site on adjoining properties and drainage paths.  


Current Activities

EPA Removal:
Completed second round of T&D of EPA stockpiled soils.  All EPA treated waste, approximately 2,340 cubic yards, has been shipped off site, thus concluding EPA T&D operations and excavation operations.  Construction of a haul road from the pad to the eastern side of the site was continued to facilitate backfilling and restoration operations.

LDEQ Removal:
LDEQ sponsored removal actions were continued.  This included excavations on the site's eastern and western portions, accounting for approximately 403.9 cubic yards of excavated soils, totalling approximately 450.02 cubic yards of in situ LDEQ soils excavated.  Excavated soils were staged in an intermediate stockpile, and then transferred to the site's western area adjacent to the pad for treatment.  Treatment of LDEQ excavated soils was initiated, accounting for approximately 79.02 cubic yards of treated soil.  Treated soil was stockpiled separately and staged for T&D.  LDEQ investigated the impoundment area by means of test pits to determine the appropriate extent of excavation.


Planned Removal Actions

EPA Removal:  Complete site restoration operations as site conditions permit.

LDEQ Removal:  Continue excavation of LDEQ sponsored grids on the eastern and western portions of the site.  Continue treatment of excavated soil.  Stage all treated soil in preparation for T&D operation.


Next Steps

LDEQ Removal: Complete LDEQ sponsored removal action and restore site.


Estimated Costs *
  Budgeted Total To Date Remaining % Remaining
Extramural Costs
Intramural Costs
 
Total Site Costs $0.00 $0.00 $0.00 0.00%

* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.


response.epa.gov/kriger_battery

POLREP #11 Last Updated 8/18/2009