POLLUTION REPORT
|
| Date: |
Tuesday, July 7, 2009
|
| From: |
Adam Adams
|
| To: |
Peter Ricca, LDEQ
|
Debbie Dietrich, EPA
|
|
Subject:
|
Continuation of LDEQ Removal Action
Kriger Battery
7179 Adams Lane,
Greenwood, LA
Latitude: 32.4374800 Longitude: -93.9434900
|
| POLREP No.: |
12
|
Site #:
|
06TH
|
| Reporting Period: |
06/28/2009 - 07/04/2009
|
D.O. #:
|
|
| Start Date: |
4/14/2009
|
Response Authority:
|
CERCLA
|
Mob Date: |
4/13/2009
|
Response Type:
|
Time-Critical
|
| Demob Date: |
|
NPL Status:
|
Non NPL
|
| Completion Date: |
|
Incident Category:
|
Removal Action
|
| CERCLIS ID #: |
LA0000605270
|
Contract #
|
EP-W-06-042
|
| RCRIS ID #: |
|
|
|
The Kriger Battery removal site is located in Greenwood, Caddo Parish, Louisiana on commercial/industrial zoned property. The site is a former battery reclamation facility that operated between 1972 and 1982 and consisted of a processing building, acid neutralization pit, and hammer mill area. Historical sampling conducted by the Louisiana Department of Environmental Quality (LDEQ)shows on-site lead concentrations as high as 112,660 mg/kg. Elevated lead concentrations have been located off-site on adjoining properties and drainage paths.
|
|
EPA Removal: No EPA activities during the reporting period.
LDEQ Removal: LDEQ sponsored removal actions were continued. Excavations were focused on the area of the former impoundment on the site's western portion, and a cavity of battery waste on the site's eastern portion. These excavations extended to depths of 72-108 inches below the original ground surface. To date, approximately 776.20 cubic yards of LDEQ soil have been excavated. Excavated soil was stockpiled on the site’s western portion. The area of the former impoundment was partially backfilled, and the site was prepared for the Independence Day break, including securing and covering all stockpiles, and staging and storing all equipment on site.
|
|
LDEQ Removal: Continue excavation of LDEQ sponsored grids on the eastern and western portions of the site. Continue treatment of excavated soil. Stage all treated soil in preparation for T&D operation.
|
|
Complete LDEQ removal action and restore site.
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
|
Intramural Costs
|
| |
| Total Site Costs |
$0.00 |
$0.00 |
$0.00 |
0.00% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
response.epa.gov/kriger_battery
POLREP #12 Last Updated 8/18/2009
|