June 26 through June, no site activities were conducted and site security concluded with all large equipment demobilized from site on June 25.
Wednesday, July 1, 2009, meeting conducted at Property G to go over MUZ use questionnaire.
Thursday, July 2, 2009, culvert, stone and dirt placed to create a walkway to the playground area from the driveway and area prepped it for concrete.
July 3 through 6, no site activities were conducted.
Tuesday, July 7, 2009, concrete installation completed for playground walkway, 2 small pads for benches by playground, walkway to boat launch, and a concrete pad for a picnic table in the southeast section of WMP.
Wednesday, July 8, 2009, no site activities were conducted.
Thursday, July 9, 2009, MUZ meeting conducted at Property F and landscaping around concrete is completed. WMP picnic table tops are painted and site benches are washed.
Friday, July 10, 2009, installation of guardrails along driveway begins. July 11 and 12, 2009, no site activities were conducted
Monday, July 13, 2009, guard rail installation completed, asphalt application on WMP driveway begins. Conducted MUZ meetings at Property D and E.
Tuesday, July 14, 2009, asphalt application completed.
Wednesday, July 15, 2009, installation of 5,000 live plants along shoreline begins. Crews remove two newly planted trees that have died.
Thursday, July 16, 2009, installation of 5,000 live plants along shoreline is completed.
Friday, July 16, 2009, installation of gravel along paved driveway is conducted. WMP grass is mowed and ECA-03 overgrown vegetation is trimmed.
Total site removal tonnage is amended to include an additional 60.45 tons that was not recorded from 6/16/2009.
|