POLLUTION REPORT
|
| Date: |
Wednesday, July 29, 2009
|
| From: |
Tom Cook
|
| To: |
John Maritote, U.S. EPA ERB
|
Mick Hans, U.S. EPA
|
|
David Chung, EPA
|
Linda Nachowicz, U.S. EPA
|
|
Afif Marouf, EPA
|
Bruce Everetts, IEPA
|
|
Mike Harris, U.S. EPA
|
Rosauro Delrosario, U.S. EPA
|
|
Peter Felitti , U.S. EPA
|
Valerie Mullins , U.S. EPA
|
|
Subject:
|
FINAL POLREP
Peoples Gas 22nd Street Station Site
2200 South Racine Avenue,
Chicago, IL
Latitude: 41.8514000 Longitude: -87.6561000
|
| POLREP No.: |
31
|
Site #:
|
B5FW
|
| Reporting Period: |
03/20/09 - 04/30/09
|
D.O. #:
|
Not Applicable
|
| Start Date: |
6/18/2007
|
Response Authority:
|
CERCLA
|
Mob Date: |
6/18/2007
|
Response Type:
|
Time-Critical
|
| Demob Date: |
4/21/2009
|
NPL Status:
|
Non NPL
|
| Completion Date: |
4/30/2009
|
Incident Category:
|
Removal Action
|
| CERCLIS ID #: |
ILD982074767
|
Contract #
|
EP-S5-06-04
|
| RCRIS ID #: |
|
|
|
See previous polreps for Site Description.
|
|
A summary of the activities performed during the reporting period by the PRP are as follows: • Completed all planned excavation activities (see BMcD map of excavation areas under "documents" on OSC website);
• Transported 6 loads of soil to CID Landfill in Calumet City, IL; all trucks decontaminated prior to leaving site;
Transported 4 loads of soil to Countryside Landfill in Grayslake IL; all trucks decontaminated prior to leaving site;
• Completed backfilling of all areas;
• Completed final grading and restoration of the site;
• The water treatment system was cleaned and demobilized from the site;
• Perimeter real-time air monitoring was discontinued on March 13th, 2009 due to the completion of excavation activities. Perimeter air sampling (24-hour air samples collected around the perimeter) utilizing PUF cartridges and Summa canisters was discontinued on March 23rd, 2009, with PM10 sampling continuing until the completion of grading activities. • Performed health and safety air monitoring (using hand-held instruments in work zones) during site activities;
• Performed street sweeping activities on Racine Street and Cermak Road;
• Completed de-watering activities in excavation areas;
• Completed water treatment; and
• Discharged 203,800 gallons of treated water to the MWRD sanitary sewer.
START did not collect any split samples with the PRP during this reporting period.
On April 21, 2009, the final site walk through was conducted. Attendees included the U.S. EPA OSC, representatives from Peoples Gas, START and the PRP contractor Burns & McDonnell.
|
|
Planned removal actions at the 22nd Street Station Site are as follows:
• There are no further planned removal actions at the 22nd Street Station Site, as the removal actions have been completed.
|
|
The next steps to be carried out by the PRP are as follows: • Submit Final Site Closure Report to the U.S. EPA.
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| RST/START |
$128,000.00 |
$114,000.00 |
$14,000.00 |
10.94% |
|
Intramural Costs
|
| |
| Total Site Costs |
$128,000.00 |
$114,000.00 |
$14,000.00 |
10.94% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
| Waste Stream |
Quantity |
Manifest # |
Disposal Facility |
| Non-hazardous Soil |
10,440 yd3 |
March 2009 |
CID RDF, Calumet City, IL |
| Non-hazardous Soil |
80.14 tons |
April 2009 |
Countryside Landfill, Grayslake, IL |