United States Environmental Protection Agency
Region VI
POLLUTION REPORT



Date:
Tuesday, August 11, 2009
From:
Steve Mason

To:
Jeff Lewellin, TCEQ
Debbie Dietrich, Office of Emergency Management
Mark Hansen, EPA Region 6

Subject: 

Initiation of Action and Final POLREP
Halliburton Plant Fire
Baroid Road, Texarkana, TX
Latitude: 32.7931910
Longitude: -96.5543750


POLREP No.:
1
Site #:
Reporting Period:
08/07/2009
D.O. #:
Start Date:
8/7/2009
Response Authority:
CERCLA
Mob Date:
8/7/2009
Response Type:
Emergency
Demob Date:
8/7/2009
NPL Status:
Non NPL
Completion Date:
8/7/2009
Incident Category:
Removal Assessment
CERCLIS ID #:
Contract #
RCRIS ID #:
 

Site Description

At approximately 1230 on Monday August 3rd, a fire occurred at the Halliburton plant in Texarkana, TX. The fire is believed to have started in a building that contained empty bags. The crew onsite attempted to put out the fire with extinguishers, and the call to the fire department went to dispatch at 1235. The fire reignited and eventually collapsed the roof. The chemicals in the building, used for the production of drilling mud, did not include any CERCLA hazardous substances, so no release was reportable under CERCLA 103. Boom was placed in the drainage areas around the site to contain the firewater runoff. The water in the drainage areas was tested and came out with a normal pH.


Current Activities

On Friday August 7, EPA OSC Steve Mason and Intern Kristen Hendrix drove to Texarkana, TX to investigate the incident further, including coordination with the City Emergency Manager, David Hall. EPA spoke with Larry Mayhan, HSE Coordinator about the fire and what exactly was in the building when it burned. EPA made recommendations to the facility concerning coordination with local emergency management during an incident, as well as media relations.


Planned Removal Actions

The RP has contracted with TAS Environmental to remove the fire debris and any cleanup necessary of waste materials.


Key Issues

None.


Estimated Costs *
  Budgeted Total To Date Remaining % Remaining
Extramural Costs
Intramural Costs
 
Total Site Costs $0.00 $0.00 $0.00 0.00%

* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.


response.epa.gov/halliburtonplantfire

POLREP #1 Last Updated 8/11/2009