United States Environmental Protection Agency
Region V
POLLUTION REPORT



Date:
Tuesday, August 18, 2009
From:
Stephen Wolfe\James Justice, On-Scene Coordinator

To:
Jason El-Zein, U.S. EPA
Mark Durno, U.S. EPA
David Chung, U.S. EPA
William Messenger, U.S. EPA ERB
Officer Duty, NRC
Robert Paulson, U.S. EPA
Michael Chezik, US Department of Interior
Kevin Clouse, OEPA
Bart Ray, OEPA
Mick Hans, US EPA
Linda Nachowicz, US EPA
Tom Williams, US EPA
Valerie Mullins, US EPA
Derek Gordon, City of Canton
Jeff Kelley, USEPA
John Glover, US EPA

Subject: 

Continuation of Removal Action
Ohio Cast Products
2408 13th Street N.E., Canton, OH
Latitude: 40.8096630
Longitude: -81.3434050


POLREP No.:
16
Site #:
B5NL
Reporting Period:
08/08/09 to 08/15/09
D.O. #:
Start Date:
3/16/2009
Response Authority:
CERCLA
Mob Date:
3/16/2009
Response Type:
Time-Critical
Demob Date:
 
NPL Status:
Non NPL
Completion Date:
 
Incident Category:
Removal Action
CERCLIS ID #:
Contract #
RCRIS ID #:
 

Site Description

See initial POLREP.


Current Activities

Daily Activities

•  ERRS continued the removal of PCB contaminated debris from the trenches inside Building #6.
•  ERRS backfilled the non-PCB impacted trenches with available on-site foundry sand.  Trenches will be capped with concrete.
•  ERRS continued pumping PCB contaminated water from the pits inside Building #6 and run the water through the on-site treatment system.  Water is stored in frac tanks pending laboratory analysis for disposal parameters.
•  ERRS continues to grade the site for final restoration.
•  START performed perimeter dust monitoring and collected perimeter dust samples for respirable silica during dust activities.  All monitoring/sampling results were less than the site’s action levels.  


Current Activities

Note: To date, approximately $18,000 was put back into the project from the recycling of on-site steel.

August 8, 2009 (Saturday) limited crew
•  ERRS graded areas covered by rock.
•  ERRS pumped PCB contaminated water from the pits inside the buildings and ran the water through the on-site treatment system.  Water is stored in frac tanks pending laboratory analysis for disposal parameters.

August 10, 2009 (Monday)
•  ERRS completed excavating pcb contaminated soil found underneath an old transformer pad area in Building #3.
•  START collected one (1) PCB confirmation soil sample from the west end of the floor of the Building #3 PCB excavation.
•  Remaining containers/lab packs/drums were transported off-site for disposal.

August 11, 2009 (Tuesday)
•  ERRS used a breaker on the pcb contaminated concrete as the concrete needs to be less than 2’x 2’ prior to T&D.

August 12, 2009, (Wednesday)
•  Two pcb transformers were transported off-site for disposal.
•  Two (2) 20-yard roll-off boxes of mixed asbestos / PCB waste transported off site for disposal.
•  Scrap steel was transported off site for recycling (including the old crane).
•  ERRS demolished the brick wall between Buildings #3 and #4, and used the brick as backfill in the Building #3 PCB excavation.

August 13, 2009, (Thursday)
•  ERRS continued the evacuation of PCB contaminated water from the trenches inside Building #6. Evacuation includes treatment and on site storage.
•  The final load of scrap steel was transported off site.

August 14, 2009, (Friday)
•  ERRS demolished the remaining (eastern portion) of the wall between Buildings #3 and #4, and used the demolition debris for backfill in the Building #3 PCB excavation.
•  ERRS scraping (removing surface debris) the concrete floors in Building #1 and #2 in preparation of the trucks for off site T&D of PCB contaminated soil nest week.

August 15, 2009, (Saturday)
•  Limited ERRS crew on site for treatment of PCB contaminated water.


Planned Removal Actions

•  Remove and dispose of PCB contaminated water from the pits associated with the building.
•  Remove and dispose of PCB contaminated sand, soils, and concrete.  
•  Performing final grading/covering of the property.


Next Steps

Analytical results were recieved for the PCB excavation areas.   Results indicated that the area inside Building #6 needed further excavation and the area in Building #3 was completed.


Estimated Costs *
  Budgeted Total To Date Remaining % Remaining
Extramural Costs
ERRS - Cleanup Contractor $1,800,000.00 $1,502,000.00 $298,000.00 16.56%
RST/START $221,000.00 $161,000.00 $60,000.00 27.15%
Intramural Costs
USEPA - Direct (Region, HQ) $225,000.00 $165,000.00 $60,000.00 26.67%
 
Total Site Costs $2,246,000.00 $1,828,000.00 $418,000.00 18.61%

* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.


Disposition of Wastes

A total of 3,144 tons of ACWM debris went to Minerva Landfill, Waynseburg, Ohio for disposal.

A total of 149 tons of mixed ACWM and PCB debris went to Minerva Landfill, Waynesburg, Ohio for disposal.

A total of 911 tons of ACWM debris went to American Landfill, Waynesburg, Ohio for disposal.

A total of 4,500 gallons of waste oil and waste quench oil went to the Chemtron Corporation for recycling/disposal.

A total of 816 tons of debris and sand contaminated with low level PCBs went to Minerva Landfill, Waynesburg, Ohio for disposal.

A total of 8 cubic yard boxes of foundry sand heavily contaminated with PCBs went to Wayne Disposal Inc., Site #2, Belleville, MI for disposal.

A total of 76 drums/totes of D001, D002 or other liquid waste went to Chemtron Corporation, Avon, Ohio for disposal.

2 PCB contaminated tranformers went to Clean Harbors, Twinsburg Ohio, for disposal.


Waste Stream Quantity Manifest # Disposal Facility
Mix ACWM and PCB  ~12 tons per load  215210 and 216794  Minerva Enterprises, Waynesburg, Ohio 
lab packs, flammable liquid  2 drums, 1 plastic tote  006249363  Chemtron Corporation, Avon, Ohio 
PCB Transformers  2  002272736  Clean Harbors, Twinsburg, Ohio 


response.epa.gov/OCP

POLREP #16 Last Updated 8/18/2009