United
States Environmental Protection Agency
Region V
POLLUTION REPORT
|
Date: |
Tuesday, August 18, 2009
|
From: |
Stephen Wolfe\James Justice, On-Scene Coordinator
|
To: |
Robert Paulson, U.S. EPA
|
|
Subject:
|
Continuation of Removal Action
Ohio Cast Products
2408 13th Street N.E.,
Canton, OH
Latitude: 40.8096630 Longitude: -81.3434050
|
POLREP No.: |
16
|
Site #:
|
B5NL
|
Reporting Period: |
08/08/09 to 08/15/09
|
D.O. #:
|
|
Start Date: |
3/16/2009
|
Response Authority:
|
CERCLA
|
Mob Date: |
3/16/2009
|
Response Type:
|
Time-Critical
|
Demob Date: |
|
NPL Status:
|
Non NPL
|
Completion Date: |
|
Incident Category:
|
Removal Action
|
CERCLIS ID #: |
|
Contract #
|
|
RCRIS ID #: |
|
|
Daily Activities
• ERRS continued the removal of PCB contaminated debris from the trenches inside Building #6. • ERRS backfilled the non-PCB impacted trenches with available on-site foundry sand. Trenches will be capped with concrete. • ERRS continued pumping PCB contaminated water from the pits inside Building #6 and run the water through the on-site treatment system. Water is stored in frac tanks pending laboratory analysis for disposal parameters. • ERRS continues to grade the site for final restoration. • START performed perimeter dust monitoring and collected perimeter dust samples for respirable silica during dust activities. All monitoring/sampling results were less than the site’s action levels.
Current Activities
Note: To date, approximately $18,000 was put back into the project from the recycling of on-site steel.
August 8, 2009 (Saturday) limited crew • ERRS graded areas covered by rock. • ERRS pumped PCB contaminated water from the pits inside the buildings and ran the water through the on-site treatment system. Water is stored in frac tanks pending laboratory analysis for disposal parameters.
August 10, 2009 (Monday) • ERRS completed excavating pcb contaminated soil found underneath an old transformer pad area in Building #3. • START collected one (1) PCB confirmation soil sample from the west end of the floor of the Building #3 PCB excavation. • Remaining containers/lab packs/drums were transported off-site for disposal.
August 11, 2009 (Tuesday) • ERRS used a breaker on the pcb contaminated concrete as the concrete needs to be less than 2’x 2’ prior to T&D.
August 12, 2009, (Wednesday) • Two pcb transformers were transported off-site for disposal. • Two (2) 20-yard roll-off boxes of mixed asbestos / PCB waste transported off site for disposal. • Scrap steel was transported off site for recycling (including the old crane). • ERRS demolished the brick wall between Buildings #3 and #4, and used the brick as backfill in the Building #3 PCB excavation.
August 13, 2009, (Thursday) • ERRS continued the evacuation of PCB contaminated water from the trenches inside Building #6. Evacuation includes treatment and on site storage. • The final load of scrap steel was transported off site.
August 14, 2009, (Friday) • ERRS demolished the remaining (eastern portion) of the wall between Buildings #3 and #4, and used the demolition debris for backfill in the Building #3 PCB excavation. • ERRS scraping (removing surface debris) the concrete floors in Building #1 and #2 in preparation of the trucks for off site T&D of PCB contaminated soil nest week.
August 15, 2009, (Saturday) • Limited ERRS crew on site for treatment of PCB contaminated water.
|
• Remove and dispose of PCB contaminated water from the pits associated with the building. • Remove and dispose of PCB contaminated sand, soils, and concrete. • Performing final grading/covering of the property.
|
Analytical results were recieved for the PCB excavation areas. Results indicated that the area inside Building #6 needed further excavation and the area in Building #3 was completed.
|
A total of 3,144 tons of ACWM debris went to Minerva Landfill, Waynseburg, Ohio for disposal.
A total of 149 tons of mixed ACWM and PCB debris went to Minerva Landfill, Waynesburg, Ohio for disposal.
A total of 911 tons of ACWM debris went to American Landfill, Waynesburg, Ohio for disposal.
A total of 4,500 gallons of waste oil and waste quench oil went to the Chemtron Corporation for recycling/disposal.
A total of 816 tons of debris and sand contaminated with low level PCBs went to Minerva Landfill, Waynesburg, Ohio for disposal.
A total of 8 cubic yard boxes of foundry sand heavily contaminated with PCBs went to Wayne Disposal Inc., Site #2, Belleville, MI for disposal.
A total of 76 drums/totes of D001, D002 or other liquid waste went to Chemtron Corporation, Avon, Ohio for disposal.
2 PCB contaminated tranformers went to Clean Harbors, Twinsburg Ohio, for disposal.
|
Waste Stream |
Quantity |
Manifest # |
Disposal Facility |
Mix ACWM and PCB |
~12 tons per load |
215210 and 216794 |
Minerva Enterprises, Waynesburg, Ohio |
lab packs, flammable liquid |
2 drums, 1 plastic tote |
006249363 |
Chemtron Corporation, Avon, Ohio |
PCB Transformers |
2 |
002272736 |
Clean Harbors, Twinsburg, Ohio |
response.epa.gov/OCP
|