July 18 through 20, no site activities were conducted.
Tuesday, July 21, 2009, barrier controls including demarcation fabric and landscape stone were completed for ECA’s 03, 04, and 05.
July 22 through 30, no site activities were conducted, WMP hydroseeded areas continue to be watered and maintained.
Friday, July 31, 2009, MUZ meeting conducted at Property J.
August 1 through 5, no site activities were conducted, WMP hydroseeded areas continue to be watered and maintained.
Thursday, August 6, 2009, Follow-up MUZ meeting conducted at Property F.
Friday, August 7, 2009, Follow-up MUZ meeting conducted at Property G. Site trailer demobilized.
August 8 through 11, no site activities conducted, WMP hydroseeded areas continue to be watered and maintained.
Wednesday, August 12, 2009, MUZ barrier control installation of stonecrete over walking path at Property G begins. Follow-up MUZ meeting conducted at Properties D and E.
Thursday, August 13, 2009, MUZ barrier control complete at Property G and MUZ barrier control installation of stonecrete over walking path begins at Property D.
August 14 through 16, no site activities were conducted, WMP hydroseeded areas continue to be watered and maintained.
Monday, August 17, 2009, playground area drainage tile is installed and playground equipment installation begins. Follow-up MUZ meeting conducted at Property J.
Tuesday, August 18, 2009, playground equipment installation complete. Second follow-up MUZ meeting conducted at Property E.
Wednesday, August 19, 2009, MUZ barrier control installation of stonecrete over walking path at Property J completed. Playground area mulch installed, MUZ area survey completed and removal of temporary site irrigation begins.
Thursday, August 20, 2009, removal of temporary site irrigation complete and grills and picnic tables installed.
Friday, August 21, 2009, WMP perimeter fencing removed and park re-opened.
|