|
United
States Environmental Protection Agency
Region V
POLLUTION REPORT
|
| Date: |
Tuesday, September 1, 2009
|
| From: |
Jon Gulch, On-Scene Coordinator
|
| To: |
David Chung, U.S. EPA
|
Jason El-Zein, U.S. EPA
|
|
Linda Nachowicz, U.S. EPA
|
Mark Durno, U.S. EPA
|
|
Beverly Kush, U.S. EPA
|
Michael Chezik, DOI
|
|
Jeff Kelley, U.S. EPA
|
Richard Murawski, U.S. EPA
|
|
William Messenger, U.S. EPA
|
Mary Jane Adamo, U.S. EPA
|
|
Mick Hans, U.S. EPA
|
Duty Officer, USCG
|
|
Kevin Clouse, Ohio EPA
|
Scott Shane, Ohio EPA
|
|
Timothy Murphy, City of Toledo
|
William Ryczek, U.S. EPA
|
|
Subject:
|
Continuation of Removal Action
Plabell Rubber Manufacturing Plant Site
300 South St. Clair,
Toledo, OH
Latitude: 41.6433000 Longitude: -83.5433000
|
| POLREP No.: |
2
|
Site #:
|
B5PX
|
| Reporting Period: |
July 31-August 14, 2009
|
D.O. #:
|
005
|
| Start Date: |
7/20/2009
|
Response Authority:
|
CERCLA
|
Mob Date: |
7/20/2009
|
Response Type:
|
Time-Critical
|
| Demob Date: |
|
NPL Status:
|
Non NPL
|
| Completion Date: |
|
Incident Category:
|
Removal Action
|
| CERCLIS ID #: |
OHN000510305
|
Contract #
|
EP-S5-08-04
|
| RCRIS ID #: |
|
|
|
See POLREP#1 for a full Site description
|
|
From July 31- August 14, 2009, EPA completed the process of searching through general debris piles in Buildings # 2 and Building #3 to identify the presence of hazardous materials. During the search, several drums, containers and bags of unknown powders were collected, staged, and field hazard categorized (HAZCAT).
During the week of August 3-7, 2009, drum sampling operations were continued and Building #2 was prepared for drum removal operations. This entailed breaking holes in the side of the building on the 3rd and 6th floors due to an inoperable freight elevator. EPA crews then moved empty drums onto the 3rd floor, which were then loaded with miscellaneous solid waste products. These drums and several full liquid drums were then removed from Building #2 with a crane.
During the week of August 10-14, 2009, the drum and container sampling operations were completed and the consolidation of materials by waste stream was started. A field chemist inventoried, staged and performed HAZCAT activities on all containers located within the research laboratory in Building #1. All hazardous and non-hazardous materials were staged near the loading dock in Building #1.
On August 14, 2009, the site was prepared for a temporary demobilization while final T&D activities were coordinated.
During all removal activities, START conducted ambient air monitoring activities both within and around the perimeter of the site for volatile organic compounds (VOC's). Prior to temporary de-mobilization and during non-working hours, a company was hired to provide security services for Site equipment and infrastructure.
|
|
Perform final disposal of all waste streams at EPA Approved Disposal Facilities.
|
|
Continue the Time-Critical Removal Action.
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| ERRS - Cleanup Contractor |
$200,000.00 |
$112,278.00 |
$87,722.00 |
43.86% |
| RST/START |
$25,000.00 |
$13,500.00 |
$11,500.00 |
46.00% |
|
Intramural Costs
|
| USEPA - Direct (Region, HQ) |
$50,225.00 |
$15,000.00 |
$35,225.00 |
70.13% |
| USEPA - InDirect |
$5,040.00 |
$0.00 |
$5,040.00 |
100.00% |
| |
| Total Site Costs |
$280,265.00 |
$140,778.00 |
$139,487.00 |
49.77% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
response.epa.gov/PlabellRubber
POLREP #2 Last Updated 9/21/2009
|