United
States Environmental Protection Agency
Region IV
POLLUTION REPORT
|
| Date: |
Monday, September 28, 2009
|
| From: |
Leonardo Ceron
|
| To: |
James Webster, Oil and Removal Program Section, ERRB, EPA
|
Jim Mcguire, Removal Program, ERRB, Superfund
|
|
Christopher Masterson, USEPA R4 ERRB
|
|
|
Subject:
|
Final Pol Rep
Goodyear Dump Site
556 Buffalo Hollow,
Berea, KY
Latitude: 37.5272000 Longitude: -84.3367000
|
| POLREP No.: |
4
|
Site #:
|
A4LP
|
| Reporting Period: |
September 28, 2009
|
D.O. #:
|
|
| Start Date: |
6/23/2009
|
Response Authority:
|
CERCLA
|
Mob Date: |
6/22/2009
|
Response Type:
|
Time-Critical
|
| Demob Date: |
9/11/2009
|
NPL Status:
|
Non NPL
|
| Completion Date: |
9/11/2009
|
Incident Category:
|
Removal Action
|
| CERCLIS ID #: |
KYN000409853
|
Contract #
|
|
| RCRIS ID #: |
|
|
|
Site operations are completed. All START and ERRS contractors and equipment have demobilized from the Site. Removal operations at this Site have removed 4,115 tons of soil and contaminated debris. All contaminated soils and debirs were disposed of in a subtitle D landfill. Approximately 3,300 cubic yards of clean backfill soils was replaced on Site. All contaminated grids were excavated and cleared for backfill, D-2, F-3, F-11, H-9, H-12, H-13, H-14, G-7, G-11, G-13, G-14, G-15, I-11, J-11. A residential septic system was replaced , two drainage areas were constructed and grading to provide runoff flow was established. Three 55 gallon drums containing paint waste were over-packed for transportation and disposed of to a subtitle D landfill.
Buffalow Hollow road was extensively damaged between the two intersections of Flat Gap road. The Rockcastel county judge executive, on behalf of the County agreed to pave the road, if EPA provided 33% of the cost for paving the entire Buffalow Hallow Road. EPA agree to pay $17,242.00 for such paving and the county has paved Buffalow Hallow road. The road repaving was completed during the week of September 8, 2009.
KDEP provide a presence on Site during the entire removal process. EPA and KDEP cooperated in all aspects of site assessment, sampling, removal and public relations for this Site.
|
|
KDEP continues to review data from the stream adjacent to the Site for potential relevant stream sediment contamination which falls below EPA’s removal action level. KDEP will determine the cost benefit of addressing these State imposed removal action levels associated with this stream.
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| ERRS - Cleanup Contractor |
$365,000.00 |
$339,720.16 |
$25,279.84 |
6.93% |
| RST/START |
$33,854.00 |
$32,915.02 |
$938.98 |
2.77% |
|
Intramural Costs
|
| |
| Total Site Costs |
$398,854.00 |
$372,635.18 |
$26,218.82 |
6.57% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
response.epa.gov/goodyeardump
POLREP #4 Last Updated 10/6/2009
|