United States Environmental Protection Agency
Region IV
POLLUTION REPORT



Date:
Thursday, October 8, 2009
From:
Richard Jardine, OSC

To:
Matt Taylor, USEPA R4 ERRB
Shane Hitchcock, USEPA R4 ERRB

Subject: 

INITIAL POLREP
FedEx Mercury Spill
2903 Sprankle St, Memphis, TN
Latitude: 35.0645607
Longitude: -89.9661307


POLREP No.:
1
Site #:
Reporting Period:
10/08/2009
D.O. #:
Start Date:
10/8/2009
Response Authority:
CERCLA
Mob Date:
10/8/2009
Response Type:
Emergency
Demob Date:
 
NPL Status:
Non NPL
Completion Date:
 
Incident Category:
Removal Action
CERCLIS ID #:
Contract #
RCRIS ID #:
 

Site Description

A faulty package leaked mercury among distribution equipment in the FedEx hub facility in Memphis. At approximately 1345 on 10/8/2009 FedEx personnel identified visible mercury on the floor and chute along one of the sorting conveyors.  The safety office and dangerous goods office were immediately notified, and personnel in the affected area were promptly evacuated.

FedEx obtained USES, subcontractor to XL Environmental, to perform the response and flew in USES response gear from Jackson, MS on a FedEx aircraft to expedite appropriate response activity.  


Current Activities

USES conducted air monitoring and collection of visible mercury.  Approximately 1 fluid ounce of free mercury was collected by 0100 10/9/2009; estimated spilled volume is 4 to 6 fluid ounces.

Affected area in distribution building includes a 30-foot package chute, 400-foot steel-strip conveyor, and the concrete floor.  Ventilation and doorways to the building were shut down between sorting periods to reduce air flow for monitoring and point source detection.

OSC Huyser and START consultant Tetra Tech responding.


Planned Removal Actions

- Assess extent of migration of mercury;
- Ensure safety of response and facility personnel;
- Conduct oversight of removal activities; and,
- Support removal activities with air monitoring and technical assistance where needed.


Estimated Costs *
  Budgeted Total To Date Remaining % Remaining
Extramural Costs
TAT/START $10,000.00 $0.00 $10,000.00 100.00%
Intramural Costs
 
Total Site Costs $10,000.00 $0.00 $10,000.00 100.00%

* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.


response.epa.gov/FedExMerc

POLREP #1 Last Updated 10/11/2009