United States Environmental Protection Agency
Region V
POLLUTION REPORT



Date:
Friday, November 6, 2009
From:
James Augustyn, On-Scene Coordinator

To:
Jason El-Zein, USEPA
David Chung, USEPA
Linda Nachowicz, USEPA
William Messenger, USEPA
NRC Duty Officer, National Response Center
Kevin Clouse, OEPA
Sally Jansen, USEPA
Mike Chezik, DOI
Mark Durno, USEPA
Nola Hicks, USEPA
Bob Princic, OEPA
Jeff Kelley, USEPA
Terry Shilling, City of Elyria

Subject: 

Time-Critical Removal Action
General Industries
154 Olive Street, Elyria, OH
Latitude: 41.3722000
Longitude: -82.0856000


POLREP No.:
2
Site #:
B5QG
Reporting Period:
10/26/09 to 11/06/09
D.O. #:
013
Start Date:
7/16/2009
Response Authority:
CERCLA
Mob Date:
10/12/2009
Response Type:
Time-Critical
Demob Date:
 
NPL Status:
Non NPL
Completion Date:
 
Incident Category:
Removal Action
CERCLIS ID #:
Contract #
68-S5-03-01
RCRIS ID #:
 

Site Description

See POLREP #1 for details


Current Activities

October 26 through October 30, ERRS continued decontaminating, removing, and loading scrap steel, removing brick debris from the northwest corner of the Site, stock piling asbestos-containing waste material (ACWM), and removing the oil layer from the 40,000 gallon subsurface vault.  The exterior, insulated pipe in the Courtyard was wrapped with visqueen to prevent accidental release of asbestos prior to cutting and removing the pipe from the exterior wall of the building.

On October 30, ERRS began loading ACWM for off-site disposal.  A total of thirty-one (31) truck loads of ACWM were loaded for off site disposal at Evergreen Landfill in Wood County, Ohio.

November 2 through November 6, ERRS continued loading ACWM for off-site disposal and continued loading and transporting scrap steel for recycling.  Began removal of surface debris from the perimeter sidewalk area.  

Activities performed by START from October 26 through November 6 included: written and photographic documentation of Site activities and conditions; observing ERRS on site removal activities, the collection of perimeter air samples for asbestos analysis, and the collection of perimeter dust monitoring readings.


Planned Removal Actions

Continue removal of scrap steel from the Site. Continue segregating, stockpiling and loading ACWM for transportation off site for disposal.


Next Steps

Removal of residual ACWM debris and impacted soil from within the ACWM area for final clearance sampling.

Removal of deteriorated roofing material from the eastern most portion of the site building.

Arrange for disposal of drummed material off site.

Disposal of liquid from the 40,000 gallon subsurface vault


Key Issues

None.


Estimated Costs *
  Budgeted Total To Date Remaining % Remaining
Extramural Costs
ERRS - Cleanup Contractor $600,000.00 $253,091.00 $346,909.00 57.82%
TAT/START $75,000.00 $45,037.00 $29,963.00 39.95%
Intramural Costs
 
Total Site Costs $675,000.00 $298,128.00 $376,872.00 55.83%

* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.


Disposition of Wastes

As of November 6, 2009:

Seventy-five (75) trucks loads, approximately 1,014 tons, of scrap steel has been transported to Bluestar Metal Recycling Company for recycling. A credit of $44,407 was put back to the Site based on the recycled steel.

One hundred thirteen (113) truck loads, approximately 2,555 tons, of ACWM has been transported to Evergreen RDF landfill in Northwood, Ohio for disposal.



response.epa.gov/GI

POLREP #2 Last Updated 11/16/2009