United States Environmental Protection Agency
Region X
POLLUTION REPORT



Date:
Monday, November 30, 2009
From:
Kathy Parker, OSC

To:
Debbie Bailey, ODEQ
Ken Itel, Clackamas County
Anthony Barber, EPA Region 10 (POLREP List)
Dan Opalski, EPA Region 10 (POLREP List)
Chris Field, EPA Region 10 (POLREP List)
Deb Yamamoto, EPA
Lori Cohen, EPA Region 10
Tara Aarnio, Oregon Iron Work

Subject: 

End of 2009 Site Work and Demobilization
Northwest Pipe and Casing
9585 Mather Road, Clackamas, OR
Latitude: 45.4149000
Longitude: -122.5200000


POLREP No.:
12
Site #:
10G8
Reporting Period:
11/8/2009 to 11/22/2009
D.O. #:
Start Date:
8/12/2009
Response Authority:
CERCLA
Mob Date:
8/12/2009
Response Type:
Time-Critical
Demob Date:
 
NPL Status:
NPL
Completion Date:
 
Incident Category:
Removal Action
CERCLIS ID #:
ORD980988307
Contract #
RCRIS ID #:
ORD980988307
 

Current Activities

This Polrep covers Site work performed from Sunday 11/8/09 through Friday 11/13/09.

Sunday 11/8/09 – no site work.

Monday 11/9/09 – no site work.

Tuesday 11/10/09 – no site work.

Wednesday 11/11/09
On-site today: 5 ERRS. Safety Meeting at 7:30am. Work ended at 5pm
* Mobilized SCBA, pressure washer, 460 Excavator, Water Truck and Forklift to site.
* Moved carbon out of GAC vessels and into cubic yard bags. Cleaned GAC vessels.

Thursday 11/12/09
On-site today: 5 ERRS. Safety Meeting at 7:30am. Work ended at noon.
* Demobilized GAC vessels.
* Level B entry into tank #1 to control vacuum truck hoses and remove sediment and water from tank. Three vacuum truck loads or sediment and water taken to Arlington landfill.
* Deconned 460 Excavator and Water Truck.
* Demobilized tank #1, Forklift, GAC vessels, pipe manifold and trench plates supporting GAC vessels.
* Returned water meter to Clackamas county.

Friday 11/13/09
On-site today: 5 ERRS. Safety Meeting at 7:30am. Work ended at 5pm
* Demobilized 460 Excavator, Water Truck, small equipment and crew.
* Secured the site for the winter.
This was the last day of site work for 2009.


Next Steps

Amend Action Memo and Task Order to transport remaining excavated soil off-site to appropriate landfill.
Grade and seed bare areas.


Estimated Costs *
  Budgeted Total To Date Remaining % Remaining
Extramural Costs
ERRS - Cleanup Contractor $2,100,000.00 $2,055,674.00 $44,326.00 2.11%
START $100,000.00 $76,061.06 $23,938.94 23.94%
Intramural Costs
 
Total Site Costs $2,200,000.00 $2,131,735.06 $68,264.94 3.10%

* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.


response.epa.gov/nwpc

POLREP #12 Last Updated 11/30/2009