During the week ending June 12, 2010, START mobilized to the Site to begin oversight of the removal activities associated with the excavation of impacted river and floodplain soil from the banks of Island 2 and Areas 3B through 5B.
During the week, Terra began installing turbidity curtains along the eastern and northern banks of Island 2; continued to assemble the water treatment system on the pad of Staging Area 1; transferred approximately 5,000 gallons of water from Staging Area 2 to Staging Area 1; and continued to remove the trees located along the banks of Island 2 and the small island located to the southwest of Island 2 (i.e., cutting, pulling, bucking, and grinding of the trees). Note: After removing the tree stumps from Island 2 and the small island, Terra hauled the stumps to the pad located at Staging Area 2. At Staging Area 2, the trees underwent additional grinding, if necessary, and were eventually hauled to the landfill.
Arcadis collected one wipe sample from the interior of the vacuum truck tank that Terra used to transfer the water from Staging Area 2 to Staging Area 1 (VT-42); and collected a total of five water samples from the water treatment system located at Staging Area 1 (W_SA1_In_001, W_SA1_RM_001, W_SA1_LM_001, W_SA1_RE_001, and W_SA1_LE_001). The analytical results for these samples were non-detect for PCB content.
During the week ending June 19, 2010, Terra continued to remove the trees located on Island 2 and the small island located to the southwest of Island 2; completed the installation of turbidity curtains along the northern side of Island 2; began and completed the installation of turbidity curtains along the southern side of the small island; installed the turbidity monitors; began to excavate riverbank soil from the northeastern side of the small island, as well as the hauling of this soil to Staging Area 2; and completed the setup of the pugmill, conveyor belt, and silo at Staging Area 1.
Terra shipped a total of 7 loads (290.91 tons) of non-TSCA soil to the C&C Landfill in Marshall, MI.
Arcadis collected seven soil samples from Island 2 (TS20339 through TS20345), and split one of these samples, TS20340, with START (Note: the START-designated name of its sample is PD2-061710-07-SD/TS20340); two surface water samples from the Kalamazoo River (TS30151 and TS30152); and one rinsate sample (TS30153). With the exception of Sample TS20345 from Grid 7, which had a total PCB content of 6.42 mg/Kg, each of the other samples had an analytical result below the cleanup criteria for PCBs (i.e., 5.0 mg/Kg). Note: After an additional six-inch excavation from Grid 7 the follow-up sample TS20360 was 0.709 mg/Kg.
Arcadis also monitored the turbidity of the river from June 16 to June 19, 2010. From approximately 1500 to 1630 on June 16, elevated turbidity readings at monitoring location TML-2 (200 feet downstream from the excavation) resulted in the inspection of the turbidity curtain along the northern side of Island 2. After determining that the turbidity curtain was intact, Arcadis attributed the elevated readings to debris that had built up on the turbidity sensor. All other downstream turbidity readings were less than twice the upstream turbidity readings.
During the week ending June 26, 2010, Terra continued to excavate riverbank soil from the northern side of Island 2; installed turbidity curtain sections along the southern bank of the small island located southwest of Island 2 and along the southwest bank of Island 2; installed turbidity curtain sections along the bank directly across from the southern side of Island 2 (Area 3B); installed silt fencing along the access road that leads from Staging Area 2 to Island 2 and from the oxbow access road to Staging Area 1; began and completed the initial excavation of riverbank soil from the small island located southwest of Island 2; and began restoration activities in Grids 1 through 6 of Island 2.
Terra shipped a total of 35 loads (1,477.22 tons) of non-TSCA soil and 11 loads (269.38 tons) of tree stumps to the C&C Landfill in Marshall, MI, and four loads (144.52 tons) of non-TSCA soil to the Ottawa Farms Landfill in Coopersville, MI.
Arcadis collected nine soil samples from Island 2 (TS20346 through TS20350 and TS20359 through TS20362); eight soil samples from the small island located southwest of Island 2 (TS20351 through TS20358), and split one of these samples, TS20353, with START (Note: the START-designated name of its sample is PD2-062210-08-SD/TS20353); eleven water samples from the water treatment system located at Staging Area 1 (W_SA1_In_002, W_SA1_RM_002, W_SA1_LM_ 002, W_SA1_RE_002, and W_SA1_LE_002, W_SA1_In_003, W_SA1_RM_003, W_SA1_LM_003, W_SA1_RE_003, W_SA1_LE_003, and W_SA1_DUP_003); one wipe sample from the vacuum truck that transported untreated water from Staging Area 2 to Staging Area 1 (VT-322); two surface water samples from the Kalamazoo River (TS30154 and TS30155); and one rinsate sample (TS30156). With the exception of Samples TS20346 and TS20362, which had analytical results of 15.8 mg/Kg and 6.66 mg/Kg, respectively, each of the other samples had an analytical result below the cleanup criteria of 5.0 mg/Kg for PCBs. Note: After an additional six-inch excavation from Grid 8 and Grid 14 of Island 2 the follow-up samples TS20359 (Grid 8) and TS20362 (Grid 14) were 0.94 and 3.0 mg/Kg, respectively. Note: Arcadis gave the initial and follow-up samples for TS20362 (Grid 14) the same name due to the fact that the initial sample material was not collected at the appropriate design depth. As such, Arcadis collected the follow-up sample from the appropriate design depth, and designated the follow-up sample with the same name as the initial sample.
Arcadis also monitored the turbidity of the river from June 21 to June 26, 2010. At approximately 1245 on June 21, an elevated turbidity reading, at monitoring location TML-3, (300 ft downstream of the excavation) resulted from the installation of turbidity curtains. All other downstream turbidity readings were less than twice the upstream turbidity readings.
During the week ending July 3, 2010, Terra completed the initial excavation of riverbank soil from all sides of Island 2; began re-excavation of the grids that had composite sample results greater than 5.0 mg/K for PCB content on Island 2; continued the installation of turbidity curtain sections in Area 3B; began installation of turbidity curtain sections in Area 4B; continued restoration activities on the northwest side of Island 2 in the cleared grids; prepared to demobilize from the Site for three days due to the July 4th holiday; began scraping the top six inches or more of the access road, on the southwestern side of Island 2, and started removing the turbidity curtain sections from the completed grids along the northern side of Island 2.
Arcadis collected thirteen soil samples from Island 2 (TS20362 (resample of original TS20362) through TS20374), and split two of these samples, TS203363 and TS20370, with START (Note: the START-designated name of its samples are PD2-062810-09-SD/TS20363 and PD2-070110-10-SD/TS20370); five water samples from the water treatment system located at Staging Area 1 (W_SA1_In_004, W_SA1_RM_004, W_SA1_LM_004, W_SA1_RE_004, and W_SA1_LE_004); two water samples from the Kalamazoo River (TS30157 and TS30158); and one rinsate sample (TS30159). With the exception of Samples TS20363 through TS20366 and Sample PD2-062810-09-SD/TS20363, which had analytical results of 11.7mg/Kg, 11.6 mg/Kg, 5.36 mg/Kg, 6.60 mg/Kg, and 8.57 mg/Kg, respectively, each of the other samples had an analytical result below the cleanup criteria of 5.0 mg/Kg for PCBs. Note: The analytical results for the follow-up samples of TS20363 through TS20366 - Samples TS2071 through TS20374 – were all below the cleanup criteria for PCBs.
Arcadis also monitored the turbidity of the river from June 26 to July 2, 2010. All downstream turbidity readings were less than twice the upstream turbidity readings.
Terra shipped a total of 23 loads (1,023.93 tons) of non-TSCA soil and three loads (85.00 tons) of tree stumps to the C&C Landfill in Marshall, MI.
|