POLLUTION REPORT



Date:
Monday, January 25, 2010
From:
Deborah Lindsey


Subject: 

Ravine - Completion of Removal Action
WRG4 Vermiculite Site
1210 Factory Street, Ellwood City, PA
Latitude: 40.8595660
Longitude: -80.3000080


POLREP No.:
25
Site #:
E358
Reporting Period:
12/14/09 - 12/31/09
D.O. #:
0703-03-009
Start Date:
7/16/2008
Response Authority:
CERCLA
Mob Date:
4/17/2008
Response Type:
Time-Critical
Demob Date:
12/22/2009
NPL Status:
Non NPL
Completion Date:
 
Incident Category:
Removal Action
CERCLIS ID #:
PAN000305592
Contract #
EP-S3-07-03
RCRIS ID #:
 

Site Description

See POLREP 21 for Site Description information


Current Activities

For the period of December 14 through December 31

On December 16, 2009, the OSC was notified that Northwest Sanitary Landfill had received an Acceptability Determination and T&D of the asbestos contaminated soils could proceed.  ERRS RM coordinated with the Northwest Sanitary Landfill to schedule transportation of the loaded roll-off boxes.  The OSC was on-site during the following dates to sign manifests and oversee pick-up of the roll-off boxes:

December 18    1 roll-off boxes   11 tons (est.) Northwest Landfill
December 22    5 roll-off boxes   51 tons (est.) Northwest Landfill

All equipment and trailers had been picked up at the time of the December 18, 2009 actions.  The ERRS RM did notify the OSC that someone had siphoned the diesel fuel from the off-road dump truck and the water truck sometime between December 12, 2009 and December 16, 2009 before being picked up by the rental company.  A police report has been filed with the Pennsylvania State Police.


Planned Removal Actions

Removal Action Complete


Next Steps

Conduct periodic inspections of cover system while researching mechanisms for Post Removal Site Controls.


Estimated Costs *
  Budgeted Total To Date Remaining % Remaining
Extramural Costs
ERRS - Cleanup Contractor $2,843,000.00 $2,581,483.00 $261,517.00 9.20%
RST/START $529,120.00 $463,164.00 $65,956.00 12.47%
Intramural Costs
 
Total Site Costs $3,372,120.00 $3,044,647.00 $327,473.00 9.71%

* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.


Disposition of Wastes


Waste Stream Quantity Manifest # Disposal Facility
Non-Hazardous Waste/soil with asbestos and vermiculite  11.18 tons  010755  Northwest Sanitary Landfill 
Non-Hazardous Waste/soil with asbestos and vermiculite  12.93 tons  010756  Northwest Sanitary Landfill 
Non-Hazardous Waste/soil with asbestos and vermiculite  10.40 tons  010757  Northwest Sanitary Landfill 
Non-Hazardous Waste/soil with asbestos and vermiculite  11.60 tons  010758  Northwest Sanitary Landfill 
Non-Hazardous Waste/soil with asbestos and vermiculite  7.55 tons  010759  Northwest Sanitary Landfill 
Non-Hazardous Waste/soil with asbestos and vermiculite  8.73 tons  010760  Northwest Sanitary Landfill 


response.epa.gov/WRG4Vermiculite

POLREP #25 Last Updated 9/28/2010