|
|
|
|
Site Number: |
A3PZ |
|
Contract Number: |
|
|
D.O. Number: |
|
|
Action Memo Date: |
9/1/2010 |
|
Response Authority: |
CERCLA |
|
Response Type: |
Time-Critical |
|
Response Lead: |
EPA |
|
Incident Category: |
Removal Action |
|
NPL Status: |
Non NPL |
|
Operable Unit: |
|
|
Mobilization Date: |
7/1/2010 |
|
Start Date: |
9/17/2010 |
|
Demob Date: |
|
|
Completion Date: |
|
|
CERCLIS ID: |
PAN000306719 |
|
RCRIS ID: |
|
|
ERNS No.: |
|
|
State Notification: |
|
|
FPN#: |
|
|
Reimbursable Account #: |
|
1.1.1 Incident Category
Time-Critical Removal
1.1.2 Site Description
The Site is characterized as a time-critical removal. The Site includes land that was used formerly for the commercial growing and harvesting of fruit from orchard trees and are currently zoned for residential or public use primarily in North Whitehall Township, PA. Lead arsenate pesticide was historically used for several decades at the Site until its use was banned in 1988 by EPA. Elevated levels of arsenic and lead have been detected in surface soil samples on residential parcels and in public use areas. The FMO Pesticide Action Memo was submitted by the OSC and signed on September 1, 2010 approving a Removal Action which addresses contamination at residential parcels.
1.1.2.1 Location
The site is located in the Orefield/Schnecksville area of North Whitehall Township, Lehigh County, Pennsylvania
1.1.2.2 Description of Threat
Incidental ingestion of lead and arsenic through direct contact with contaminated soil, or ingestion of contaminants from small particles that have been aerosolized from the disturbance of soil.
|
|
|
|
2.2.1 Anticipated Activities
ERRS will remobe to the site on 8/21 and resume excavation activities.
Property specific work plans for residences requiring soil excavation will continue to be prepared. EPA will be meeting and scheduling with residents where removal activities may take place. At times scheduled between the resident and EPA, excavation of properties will occur, samples will be collected, backfill installed, and sod installed.
Air monitoring will not be conducted during the demobe period.
Samples will be shipped to an offsite laboratory for Post-Excavation activities. For any newly added removal action properties, Extent of Contamination samples will be collected and shipped off-site to a laboratory for analysis. This will provide quicker results and enable the action to be taken this year. These samples will be shipped for offsite analysis. ERRS will continue to water sod during the demobe period.
EPA will prepare closeout letters for those properties where we have received validated data for post-excavation sampling. Letters will include maps showing where EPA excavated and restored the property and a table of post excavation sampling results. Post-excavation walkthroughs are being scheduled at residences at which excavation activities have been completed.
Upon receipt of the validated Phase II data from the samples collected this week, the property owner will be provided the results. Upon receipt of validated data from the extent of contamination samples collected this week, EPA will evaluate the data and determine excavation areas and the proper course of action for removal action.
2.2.1.2 Next Steps
2.2.2 Issues
The lack of rain and severe heat continues to complicate the stablization of the new sod and the restoration of properties. Sod watering has been increased because during the period of initial rooting (approximatley 3 weeks), EPA is continues to irrigate the sod using water trucks.watering lawns twice a day for fours weeks, and at least once a day after that to avoid sod failure.
Recently the Township roadmaster informed the ERRs Response Manager of a resurfacing project within the Schnecksville area. Creekview Drive is one of the streets scheduled for resurfacing in early September. EPA will need to stay off that street for approximately one month. Several properties are still slated for a removal action on Creekview Drive in Schnecksville, PA. These properties may have to be moved to the spring of next year. The OSC and ERRs contractor will continue to coordinate with the Township on this project.
|
|
|
On July 24th, 2011, 2 Kemron personnel were onsite.
On July 25th, 2011, 11 Kemron, 2 Weston, 3 Sod Works, and 1 EPA personnel were onsite
On July 26th, 2011, 11 Kemron, 2 Weston, and 2 EPA personnel were onsite
On July 27th, 2011, 11 Kemron, 2 Weston, and 2 EPA personnel were onsite
On July 28th, 2011, 11 Kemron, 2 Weston, and 2 EPA personnel were onsite
On July 29th, 2011, 8 Kemron, 1 Weston, and 2 EPA personnel were onsite
On July 30th, 2011, 2 Kemron personnel were onsite
On July 31st, 2011, 2 Kemron personnel were onsite
On August 1st, 2011, 4 Kemron, 4 Sod Works, 2 Weston, and 1 EPA personnel were onsite
On August 2nd, 2011, 4 Kemron, 4 Sod Works, and 2 EPA personnel were onsite
On August 3rd, 2011, 4 Kemron, 3 Sod Works, and 1 Weston personnel were onsite
|