POLLUTION REPORT
|
| Date: |
Saturday, August 28, 2004
|
| From: |
Chris Russell
|
| To: |
Chris Russell, USEPA-Region IV/ERRB
|
Matt Taylor, ERRB
|
|
Dean A. Ullock, EPA
|
Ken Mills, USCG-Gulf Strike Team
|
|
Shane Raiford, USGS-GST
|
Shane Hitchcock, USEPA-Region IV/ERRB
|
|
Phil Davis, ADEM
|
|
|
Subject:
|
Removal Progress
Mobile Tank Wash Site
1051 Ledyard St.,
Mobile, AL
Latitude: 30.6670600 Longitude: -88.0491500
|
| POLREP No.: |
6
|
Site #:
|
A4DQ
|
| Reporting Period: |
6/26/2004 - 8/28/2004
|
D.O. #:
|
TBD
|
| Start Date: |
4/5/2004
|
Response Authority:
|
CERCLA
|
Mob Date: |
4/4/2004
|
Response Type:
|
Time-Critical
|
| Demob Date: |
|
NPL Status:
|
Non NPL
|
| Completion Date: |
|
Incident Category:
|
Removal Action
|
| CERCLIS ID #: |
ALD980708036
|
Contract #
|
|
| RCRIS ID #: |
|
|
|
Please refer to Initial POLREP.
|
|
During this reporting period, EPA, ERRS, START, and USCG/GST, continued to open and sample the contents of the abandoned drums and containers on site. Over 900 samples have been collected. These samples were sent to the lab for analysis. In turn, 15 waste streams were identified, of those, 12 are hazardous.
The bulking of wastes has begun and several hundred drums have been bulked into like waste steams. All free liquids have been bulked into like waste groups and ERRS is currently removing the sludges left in the drums. Three sludge boxes full of non-hazardous sludge have been removed thus far.
During this period, a sampling plan was devised and carried out. The analysis associated with the samples is currently being reviewed.
EPA has attended two monthly meetings and provided updates to the citizens group: Oakdale Community Development Program.
|
|
Continue bulking wastes into like waste streams.
Remove two UST's located on site, as well as three AST's on site.
|
|
-Removal of sludges in the drums.
-Request bids for disposal of the 15 waste streams.
-Request bids for crane services associated with removing the AST's.
|
|
High public and media interest.
Physical concerns due to heat.
Physical condition of the drums and the dangers associated with moving them.
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| ERRS - Cleanup Contractor |
$850,000.00 |
$641,100.00 |
$208,900.00 |
24.58% |
| IAGs |
$75,000.00 |
$38,000.00 |
$37,000.00 |
49.33% |
| RST/START |
$94,000.00 |
$88,000.00 |
$6,000.00 |
6.38% |
|
Intramural Costs
|
| USEPA - Direct (Region, HQ) |
$86,000.00 |
$60,000.00 |
$26,000.00 |
30.23% |
| |
| Total Site Costs |
$1,105,000.00 |
$827,100.00 |
$277,900.00 |
25.15% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
response.epa.gov/mobiletankwash
POLREP #6 Last Updated 8/28/2004
|