September 6, 2004: Labor Day Holiday September 7, 2004: 1 OSC, 1 PST, 2 START, 4 ERRS; ERRS continuing to consolidate potentially clean items into lots for assessment by the START. ERRS began to build shielding for a low background area. START conducting air surveillance. The START updating Consolidated HASP. September 8, 2004: 1 OSC, 1 PST, 2 START, 4 ERRS; ERRS continuing to consolidate potentially clean items into lots for assessment by the START. ERRS continued to build shielding for a low background area. START conducting air surveillance. September 9, 2004: 1 OSC, 1 PST, 2 START, 4 ERRS; ERRS continuing to consolidate potentially clean items into lots for assessment by the START. ERRS finished building the shielding for a low background area. START conducting air surveillance. The START conducted gamma screening of 50 lots of items. Several radium containing dials were detected. September 10, 2004: 1 OSC, 1 PST, 1 START, 4 ERRS; ERRS continuing to consolidate potentially clean items into lots for assessment by the START. START conducting air surveillance. The START conducted alpha screening of 50 lots for fixed and removable alpha contamination. Several contaminated items were discovered and placed with the other radium containing items.
|