U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
Zonolite Road Atlanta GAO144 - Removal Polrep
Final Removal Polrep

EPA Emergency Response

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region IV

Subject: POLREP #12
Final POLREP
Zonolite Road Atlanta GAO144
B407
Atlanta, GA
Latitude: 33.8063720 Longitude: -84.3417654


To:
From: Kevin Eichinger, OSC
Terry Stilman, OSC
Date: 2/27/2012
Reporting Period: February 16, 2012 through May 7, 2012

1. Introduction
  1.1 Background
   
Site Number: B407    Contract Number:  
D.O. Number:      Action Memo Date: 4/8/2011
Response Authority: CERCLA    Response Type: Time-Critical
Response Lead: PRP    Incident Category: Removal Action
NPL Status: Non NPL    Operable Unit:
Mobilization Date: 6/1/2011    Start Date: 6/1/2011
Demob Date: 2/24/2012    Completion Date: 3/2/2012
CERCLIS ID:    RCRIS ID:
ERNS No.:    State Notification:
FPN#:    Reimbursable Account #:

1.1.2 Site Description

A removal site evaluation indicating that the Zonolite Road Site be given priority for removal eligibility was completed on March 23, 2011.   The Site, also referenced as the “GAO 144 site” was the former location of a vermiculite expansion (or, exfoliation) plant.  According to the previous owner and operator, the expansion plant operated from 1950 until 1970 and received between 499 and 1,225 tons of vermiculite concentrate from the W.R. Grace vermiculite mine in Libby, Montana. 

 1.1.2.1 Location

The Site is located approximately 4.5 miles northeast of downtown Atlanta, Georgia, in a developed urban area of mixed light-industrial, commercial, and residential use.  The site occupies about 16 acres, some or all of which was the former location of a vermiculite expansion plant.  The Site is bordered to the south by Dalon Road, a landscape services and garden business, and the south fork of Peachtree Creek.  To the west of the Site are Peachtree Creek and several residences.  The Site is bordered to the north by railroad tracks and a complex containing numerous commercial and light industrial businesses.  Residential communities are located to the south beyond the south fork of Peachtree Creek, to the west, and to the north beyond the railroad tracks.  
 

2. Current Activities
  2.1 Operations Section
   
2.1.2 Response Actions to Date Summary 

In October 2011, W.R. Grace initiated a removal action at the GAO 144 site in Atlanta, Georgia. Activities included the collection and analysis of bulk material samples to further characterize site conditions; excavation of areas surrounding the north and south concrete pads; cleaning of the concrete pads where possible vermiculite migration occurred during removal activities and collection of air samples using ABS techniques from within the excavated areas. During the removal action, W.R. Grace hired Winter, URS, and One Group to complete field activities. EPA provided oversight and Tetra Tech START provided technical assistance, perimeter particulate monitoring; documentation of removal activities and co-located ABS samples for laboratory analysis. On February 24, 2012, W.R. Grace and its contractors completed removal activities. Approximately 26,000 tons of asbestos and vermiculite contaminated soil and material has been removed and sent offsite for disposal to the Waste Management Landfill in Ball Ground, Georgia. Soil removal operations are complete.  Activity based sampling was conducted through-out the site. No asbestos was detected above health based site specific clearance levels.  Site restoration activities are complete.  The site has been graded and restored to DeKalb County specifications. 

The following final site activities occurred since EPA's last POLREP:

April 27,2012 -
Per the terms of the Administrative Order of Consent, W.R. Grace submitted a Final Report for the Removal Action at the Zonolite Road Site to EPA. The final report detailed all aspects of the removal action, including air and soil sample results and waste disposal manifests.

April 11, 2012 - EPA's START Contractor, Tetra Tech, submitted a letter report summarizing actions taken at the Zonolite Site. The report included figures and tables detailing the air and soil sample locations and results .

March 26, 2012 - OSC's Eichinger and Stilman met on site with Dave Butler, Greenspace Manager for DeKalb County to discuss the project close out. The preliminary ABS sampling data and locations were provided to Dave Butler. Dave Butler was satisfied with the results of the Removal Action. Control of access to the site was returned to DeKalb County.

March 24, 2012 -
The South Fork Conservancy hosted the 2012 Park Pride Conference. An afternoon tour of the Zonolite site was included in the conference program. OSC Eichinger and Dave Butler provided the tour participants with the history of the remediation.

March 19, 2012 - OSC Eichinger coordinated and hosted a site meeting to review the removal and restoration work. Representatives from EPA, START, DeKalb County and the South Fork Conservancy attended.

March 1 2012 - South Fork sediment samples were received. Those sample results show non detect for asbestos; confirming that migration of site contaminants did not enter into South Fork of the Peachtree Creek during removal activities.  

February 24, 2012 - The rental equipment company picked up the remaining equipment.  The fencing company was brought in to repair the portion of the entrance gate that was damaged by truck. START and OSC Stilman performed sediment sampling (3 locations and 1 background) in the South Fork of the Peachtree Creek in the area of the drainage creek outfall.  Samples were sent out for asbestos analysis. 

February 23, 2012 - Activity based clearance sampling of the building pads occurred. Perimeter and personnel sampling continues. No asbestos was detected in the personnel or perimeter air samples. Air sample were sent to the laboratory with a two day turn around time for the results.  No asbestos was detected in personnel or perimeter air samples.  START, OSC Berry and OSC Stilman provided oversight  

February 22, 2012 - Crews continued to restore the site and follow the grading plan provided by DeKalb County. Rip-rap and corrosion control matting was installed on the new bank of drainage creek. All exposed soil was hydro-seeded.

February 21, 2012 - Crews continued to restore the site and follow the grading plan provided by DeKalb County 

February 20, 2012 - Crews continued to restore the site and follow the grading plan provided by DeKalb County 

February 17, 2012 -
The final 450 tons of asbestos contaminated soil was removed and shipped off site for disposal. Perimeter and personnel sampling continues. No asbestos was detected in personnel or perimeter air samples. Crews continued to restore the site and follow the grading plan provided by DeKalb County

February 16, 2012 - W.R. Grace continued with site restoration activities. Numerous loads of fill dirt where delivered.  Crews are grading to specifications provided by DeKalb County.


  2.2 Planning Section
    2.2.1 Anticipated Activities

Removal actions completed, no additional activities anticipated.

  2.3 Logistics Section
    No information available at this time.

  2.4 Finance Section
    No information available at this time.

  2.5 Other Command Staff
    No information available at this time.

3. Participating Entities
  3.2 Cooperating Agencies

Dekalb County

4. Personnel On Site
  The following personnel were onsite at various times through out the reporting period:

EPA - 3
DeKalb County Natural Resources - 1
AECOM - 1
START - 3
URS - 2
W.R. Grace (Remedium Group) - 1
One Group Consulting - 4
Winter Environmental - 25

5. Definition of Terms
  ABS - Activity Based Sampling - Collecting of air samples while engaging in dust generation activities that could disturb asbestos fibers and release them into the air.

OSHA - Occupational Safety and Health Administration - an agency of the United States Department of Labor whose mission is to prevent work-related injuries, illnesses, and occupational fatality by issuing and enforcing standards for workplace safety and health.

PCM - Phase Contrast Microscopy - Sample analysis procedure, following NIOSH Analytical Method 7400, used to determine the presence of fibers in air samples.  This procedure does not differentiate between non-hazardous fibers and asbestos fibers.  Used to determine the effectiveness of engineering controls and work practices during the actual removal of the asbestos contaminated material. 

PEL - Permissible Exposure Limit - Legal limit in the United States for worker exposure to a chemical substance or physical agent.

TEM - Transmission Electron Microscopy - Sample analysis procedure, following NIOSH Method 7402, used to determine the presence, type and concentration of asbestos in air samples.

6. Additional sources of information
  No information available at this time.

7. Situational Reference Materials
  No information available at this time.