1. Introduction
|
|
1.1 Background
|
|
|
Site Number: |
A3SZ |
|
Contract Number: |
EP-S3-12-03 |
D.O. Number: |
1 |
|
Action Memo Date: |
4/27/2012 |
Response Authority: |
CERCLA |
|
Response Type: |
Time-Critical |
Response Lead: |
EPA |
|
Incident Category: |
Removal Action |
NPL Status: |
Non NPL |
|
Operable Unit: |
|
Mobilization Date: |
5/9/2012 |
|
Start Date: |
5/19/2012 |
Demob Date: |
|
|
Completion Date: |
|
CERCLIS ID: |
VAN000306849 |
|
RCRIS ID: |
|
ERNS No.: |
|
|
State Notification: |
|
FPN#: |
|
|
Reimbursable Account #: |
|
1.1.1 Incident Category
Time-critical removal action.
1.1.2 Site Description
On November 21, 2011, an arson fire destroyed a 300,000 square foot brick, timber, and steel warehouse building on Trent Hill Drive in Henry County, Virginia. The warehouse, formerly used by the Bassett Furniture Company, was owned by a non-profit entity which used it to store items for distribution to charities. The fire resulted in the collapse of approximately half of the building leaving a debris pile of roughly 5 acres. While investigating the fire, suspected asbestos-containing material (ACM) was identified by local responders. On December 1, 2011, Virginia Department of Emergency Management (VADEM) called the National Response Center (NRC) and reported the findings of potential ACM. EPA responded to the report and VADEM requested assistance with assessing the situation.
1.1.2.1 Location
Bassett, Henry County, Virginia.
1.1.2.2 Description of Threat
Friable asbestos containing materials (ACM) exposed to the environment.
1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results
During the fire investigation, suspected ACM was spotted. Virginia Department of Labor and Industry (VADOLI) mobilized to Site and confirmed, via visual characterization, that there was significant asbestos materials present in the rubble of the building. EPA performed two sampling events, an initial assessment was performed in December 2011 and additional sampling occurred in January 2012. Samples collected during both events at the Site revealed the presence of material containing up to 40 % friable asbestos in the debris located throughout the Site.
|
2. Current Activities
|
|
2.1 Operations Section
|
|
|
2.1.1 Narrative
An action memorandum was signed on April 27, 2012 authorizing EPA to begin fund lead removal activities at the Old Bassett Warehouse Fire Site.
2.1.2 Response Actions to Date
ERRS continued to properly dispose of ACM offsite. Personnel and perimeter air sampling and real time air monitoring continued daily as well as constant wetting continues in the work areas to minimize dust and comply with the substantiative requirements of NESHAPs. Off-site disposal of ACM was completed on 7/19/2012. A total of 6,393 tons was transported off-site for disposal.
Once all ACM was removed from the building footprint, additional decontamination of the building pad was performed. This decontamination included cleaning with a sweeper machine and washing the pad. Additional decontamination was also performed on the remaining steel that was stockpiled on-site for disposal. Water generated during these activities was containerized and triple filtered, sampled, and then discharged to the publicly owned treatment works (POTW). Approximately 600 gallons of water was discharged to the local POTW.
ERRS continued demobilizing personnel and equipment from the Site. All personnel and equipment are expected to be demobilized from the site by August 6, 2012 .
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
Resource Exchange Associates has been identified as the owner of the building in question.
2.1.4 Progress Metrics
Waste Stream |
Medium |
Quantity |
Manifest # |
Treatment |
Disposal |
ACM Material
|
brick/soil |
817 tons
|
various |
N/A |
X
|
|
|
|
|
|
|
|
TOTAL TO DATE:
|
6,393 tons
|
|
|
|
|
|
2.2 Planning Section
|
|
|
2.2.1 Anticipated Activities
All on-site work is expected to be completed by August 6, 2012. Final invoices and reports will be prepared.
2.2.1.2 Next Steps
Both START and ERRS will submit final invoices and complete final site reports.
2.2.2 Issues
Asbestos falls under a nationally significant or precedent setting issue and EPA headquarters has concurred with the action memorandum.
|
|
2.3 Logistics Section
|
|
|
No information available at this time.
|
|
2.4 Finance Section
|
|
|
No information available at this time.
|
|
2.5 Other Command Staff
|
|
|
No information available at this time.
|
3. Participating Entities
|
|
No information available at this time.
|
4. Personnel On Site
|
|
EPA: 1 On Scene Coordinator
1 EPA Site Administrative Officer
ERRS: 1 Response Manager
1 Field Cost Accountant
1 Cleanup Technicians
1 Truck Driver
START: 1 Environmental Technician
|
5. Definition of Terms
|
|
ACM
CERCLA |
Asbestos containing material
Comprehensive Environmental Response, Compensation, and Liability Act |
EPA
ERRS |
Environmental Protection Agency
Emergency and Rapid Response Services |
f/cc
HASP
NESHAPS
OSC
PCM
POLREP
POTW
PPE
PRP
START |
Fibers per cubic centimeter
Health and Safety Plan
National Emission Standards for Hazardous Air Pollutants
On-Scene Coordinator
Phase Contrast Microscopy
Pollution Report
Publicly Owned Treatment Works
Personal Protective Equipment
Potentially Responsible Party
Superfund Technical Assessment and Response Team
|
TEM
VADEM
VADEQ
VADOLI |
Transmission Electron Microscopy
Virginia Department of Emergency Management
Virginia Department of Environmental Quality
Virginia Department of Labor and Industry
|
|
|
|
|
|
|
|
|
|
6. Additional sources of information
|
|
No information available at this time.
|
7. Situational Reference Materials
|
|
No information available at this time.
|