United States Environmental Protection Agency
Region VI
POLLUTION REPORT



Date:
Wednesday, October 20, 2004
From:
Charles Fisher


Subject: 

& Final
Wolsey Well Service Oil Spill
1624 Highway 59 N, Bowie, TX
Latitude: 33.6708300
Longitude: -97.8294300


POLREP No.:
1
Site #:
1134
Reporting Period:
D.O. #:
Start Date:
10/17/2004
Response Authority:
OPA
Mob Date:
10/18/2004
Response Type:
Emergency
Demob Date:
10/18/2004
NPL Status:
Non NPL
Completion Date:
10/18/2004
Incident Category:
Removal Assessment
CERCLIS ID #:
Contract #
RCRIS ID #:
Reimbursable Account #
FPN#
E05601
 

Site Description

On October 17, 2004, the National Response Center (NRC) was notified of a discharge of an unknown quantity of crude oil and salt water (NRC Report No. 738626) from an onshore oil production facility located near Bowie, Montague County, Texas.  The caller indicated that a faulty valve in the oil/water separator malfunctioned resulting in the discharge.  On October 17, 2004 the NRC notified the EPA Region 6 Response and Prevention Branch (EPA RPB).  On October 17, 2004, the EPA RPB activated the EPA Region 6 Superfund Technical Assessment and Response Team (START-2) contractor to mobilize to the site on October 18, 2004 and initiate all relevant response actions.  


Current Activities

On October 18 2004, START-2 contractors mobilized to the site and met with representatives of Wolsey Well Service, Inc, the Potentially Responsible Party (PRP) and property owners.  According to the PRP representative, on October 17, 2004, a float valve in the oil/water separator became stuck causing an overflow of the separator and the discharge of crude oil and salt water.  The discharged crude oil and salt water flowed northeast approximately 500 feet and entered an unnamed intermittent creek which is currently dry.  The crude oil and saltwater then flowed approximately 1000 feet down the creek bed.  Approximately 60 barrels of crude oil was recovered from the creek with vacuum trucks on October 17, 2004 and transferred to crude oil storage tanks onsite. Two earthen dams were constructed downstream of the discharge in the creek to prevent further migration of the oil and salt water.  START-2 observed no oil in the creek downstream of the earthen dam.  PRP-led cleanup crews were onsite washing the remaining crude oil and salt water in the spill pathway and creek bed with water to flush the oil to a collection point where the water and oil is being collected and removed with vacuum trucks.


Next Steps

EPA will coordinate with the Texas Commission on Environmental Quality (TCEQ) and Texas Railroad Commission (TRRC) to monitor cleanup efforts at the site..


Key Issues

None


Estimated Costs *
  Budgeted Total To Date Remaining % Remaining
Extramural Costs
Intramural Costs
 
Total Site Costs $0.00 $0.00 $0.00 0.00%

* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.


response.epa.gov/WolseyWell

POLREP #1 Last Updated 10/21/2004