The Yerington/Anaconda Mine Site is an abandoned copper mining, milling, and processing facility. It covers 3,468 acres and is located two miles north of Yerington, Nevada.
The Anaconda Copper Company operated the mine from 1952 to 1978 as a low-grade copper mine and milling operation. During this period, a total of 350 million tons of ore and waste rock were mined form the Yerington Pit, and 189 tons of waste was generated.
In 1977 the Atlantic Richfield Company acquired Anaconda and assumed its operations at the Site. In June 1978, Atlantic Richfield terminated operations at the Site. In or about 1982, Atlantic Richfield sold its interests in the private lands within the Site to Don Tibbals, a local resident, who subsequently sold his interests with the exception of the Weed Heights community to Arimetco, Inc. Arimetco operated a copper recovery operation from existing ore heaps within the Site from 1989 to November 1999. Arimetco terminated operations and filed bankruptcy.
The site consists of a process facility, an open-pit mine, an overburden dump, sulfide and oxide stockpile dumps, leach pads, tailings and waste rock piles, and evaporation ponds. Naturally occurring radioactive materials including uranium, thorium, and radium, are present at the site and have become concentrated in some areas due to mining processes.
To date, EPA has conducted five separate removal actions at the site. An initial removal action was conducted at the site in February 2006. This removal action consisted of two phases of work. The first phase involved the removal of approximately 120 PCB-containing transformers. The second phase of this removal action involved addressing fugitive dust at the site. This work, which was conducted from April 5 to May 12, 2006, primarily involved placing a soil cap over approximately 75 acres of exposed sulfide tailings.
EPA conducted a second removal action at the site from August to October 2006. This removal action addressed fluids management problems associated with the Arimetco heap leach system. EPA conducted the following activities: construction of a 4-acre evaporation pond, construction of an 1,100 foot french drain intended to capture heap draindown before it enters the Megapond, and relining of Slot Pond #2.
EPA conducted a third removal action at the site in October 2007. This removal action addressed the Bathtub Pond of the fluids management system. EPA removed the sediments and liner from the pond, backfilled and compacted the pond area, and installed a french drain to collect the heap leach fluids draining down from the adjacent heap.
In September 2008, EPA completed a fourth removal action. This project included closure of the following heap leach ponds: South Slot Pond, Plant Feed Pond, Old Raffinate Pond, New Raffinate Pond and the Megapond. In the case of the the Old Raffinate Pond, kerosene contaminated soils exist beneath the pond to a depth of more than 20 feet. These contaminated soils will were excavated and bioremediated onsite. Bioremediation of these kerosene contaminated soils was completed in June 2010. EPA also relined the Phase I/II Pond and repair the VLT Pond, as both of these ponds were still needed to capture heap leach draindown fluids. .
In May and June 2009, EPA conducted a fifth removal action. Asbestos containing material in the Anaconda Mine Office was removed and disposed of offsite. Following removal of the asbestos, the building was demolished and placed in an onsite construction debris landfill. A tire pile, consisting of more than 300 large tires, was screened for radioactive contaminants and the tires were sent offsite for disposal/re-use.
On April 21, 2009, EPA and the Atlantic Richfield Company (ARC) signed an Administrative Order on Consent under which ARC agreed to conduct four removal actions: removal of electrical hazards, removal of radiological soil contamination, removal of transite pipe and capping of two areas (Thumb Pond and Sub Area A). The electrical hazards removal action was completed in advance of the other actions. From 10/20/2009-12/13/2010, all activities related to the remaining three removal actions were completed by ARC. START and EPA personnel were onsite to oversee cleanup activities.
On September 5, 2012, EPA mobilized to the site to conduct an additional removal action. This removal action is being funded by the Atlantic Richfield Company and Quaterra Resources (the current owner of the property), under separate agreements with EPA. This removal action will include relining the VLT heap leach pond and making repairs to certain areas of the heap leach perimeter ditch system.
|