POLLUTION REPORT
|
| Date: |
Thursday, November 4, 2004
|
| From: |
Harry Allen IV
|
| To: |
Harry L. Allen, U.S. EPA Region 9
|
Harry Allen, Environmental Response Team
|
|
Michael Daniel, GRIC Department of Environmental Quality
|
Wenona Wilson, U.S. EPA Region 9
|
|
Pat Mariella, GRIC Dept. of Env. Quality
|
Gwen Eng, ATSDR
|
|
Eleanor Vargas, GRIC Public Health
|
Daniel Meer, EPA R9
|
|
Peggy DeLaTorre, EPA R9
|
Eugene Rainwater, EPA R9
|
|
Pat Port, Dept of Interior
|
Mark Merchant, EPA R9 ERS
|
|
Celeste Temple, EPA R9 ERS
|
Mark Mjoness, EPA HQ
|
|
Lisa Boynton, EPA HQ
|
|
|
Subject:
|
Follow-up Sampling Event
Gila River Boundary
51st Avenue and Komatke Lane,
Laveen, AZ
Latitude: 33.3239304 Longitude: -112.1724701
|
| POLREP No.: |
5
|
Site #:
|
0963
|
| Reporting Period: |
Summer and Fall 2004
|
D.O. #:
|
|
| Start Date: |
4/15/2004
|
Response Authority:
|
CERCLA
|
Mob Date: |
4/14/2004
|
Response Type:
|
Time-Critical
|
| Demob Date: |
|
NPL Status:
|
Non NPL
|
| Completion Date: |
|
Incident Category:
|
Removal Action
|
| CERCLIS ID #: |
AZD981621881
|
Contract #
|
|
| RCRIS ID #: |
|
|
|
Construction of six treatment cells, or burritos, was completed in May 2004. Later that month, 3 soil samples were collected from each of the cells to document toxaphene concentrations prior to treatment.
During the summer the Site was monitored by contractors. Contractors maintained the chain-link fence surrounding the Site.
Follow-up soil sampling was conducted on September 27, 2004. Preliminary results indicated that 5 of the 6 treatment cells met the toxaphene cleanup concentration goal. These cells are considered to be finished. The 6th treatment cell did not meet the cleanup goal.
Mean concentrations for all cells fell by 51 to 88% so far. More time will be allowed for further degradation to take place.
|
|
Once all of the treatment cells have met the Site action level for toxaphene, the cells will be uncovered, drained and the Site will be regraded.
|
|
A second follow-up sampling event is planned for December 2004. Should the 6th cell meet the action level, a treatment cell decommisioning event will be planned and executed.
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| ERRS - Cleanup Contractor |
$675,000.00 |
$400,100.00 |
$274,900.00 |
40.73% |
|
Intramural Costs
|
| |
| Total Site Costs |
$675,000.00 |
$400,100.00 |
$274,900.00 |
40.73% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
response.epa.gov/GilaBoundary
POLREP #5 Last Updated 11/4/2004
|