|
United
States Environmental Protection Agency
Region X
POLLUTION REPORT
|
| Date: |
Friday, November 5, 2004
|
| From: |
Michael Szerlog
|
| To: |
NPFC Polreps, USCG (POLREP List)
|
Anthony Barber, EPA Region 10 (POLREP List)
|
|
Dan Opalski, EPA Region 10 (POLREP List)
|
Eugene Lee, EPA HQ (POLREP List)
|
|
Chris Field, Region 10 List - EPA Region 10
|
Steve Heaton, IDEQ - LUST Program
|
|
Wally Moon, EPA - UST Program
|
Miguel Bella, USCG
|
|
James Werntz, EPA
|
|
|
Subject:
|
Progress
Ashton Texaco Oil Release
363 Highway 20,
Ashton, ID
Latitude: 44.0750000 Longitude: -111.4600000
|
| POLREP No.: |
17
|
Site #:
|
Z0A3
|
| Reporting Period: |
10/1-10/31/04
|
D.O. #:
|
64-10-17
|
| Start Date: |
5/27/2003
|
Response Authority:
|
OPA
|
Mob Date: |
5/27/2003
|
Response Type:
|
|
| Demob Date: |
|
NPL Status:
|
Non NPL
|
| Completion Date: |
|
Incident Category:
|
Removal Action
|
| CERCLIS ID #: |
|
Contract #
|
|
| RCRIS ID #: |
IDR000201400
|
Reimbursable Account #
|
Z0A3
|
| FPN# |
E03012
|
|
|
October 1 through 9, 2004: ERRS Subcontracotr (1) ERRS Subcontractor conducted operations and maintenance activities. A total of 187 gallons of material recovered to date in the 1,000 gallon tank.
October 10 through 16, 2004: ERRS Subcontracotr (1) ERRS Subcontractor conducted operations and maintenance activities. A total of 187 gallons of material recovered to date in the 1,000 gallon tank.
October 17 through 23, 2004: ERRS Subcontracotr (1) ERRS Subcontractor conducted operations and maintenance activities. A total of 188 gallons of material recovered to date in the 1,000 gallon tank.
October 24 through 31, 2004: ERRS Subcontracotr (1) ERRS Subcontractor conducted operations and maintenance activities. A total of 189 gallons of material recovered to date in the 1,000 gallon tank.
|
|
-Continue to recover oil.
|
|
-Transportation and Disposal of recovered product as needed. - EPA and IDEQ will review data to date and made recommendations for next year.
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| ERRS - Cleanup Contractor |
$180,000.00 |
$173,229.00 |
$6,771.00 |
3.76% |
| RST/START |
$100,000.00 |
$95,980.00 |
$4,020.00 |
4.02% |
| PRFA - IDEQ |
$20,000.00 |
$19,435.00 |
$565.00 |
2.83% |
|
Intramural Costs
|
| USEPA - Direct (Region, HQ) |
$30,000.00 |
$19,600.00 |
$10,400.00 |
34.67% |
| |
| Total Site Costs |
$330,000.00 |
$308,244.00 |
$21,756.00 |
6.59% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
response.epa.gov/AshtonTexaco
POLREP #17 Last Updated 11/5/2004
|