Date:
Friday, December 3, 2004
From:
Amy Feingold


Subject: 

Loflin Gold Mine
Loflin Hill Road, Trinity, NC
Latitude: 35.7250000
Longitude: -80.0433000


POLREP No.:
8
Site #:
A4AE
Reporting Period:
11/29/2004 - 12/03/2004
D.O. #:
Start Date:
10/19/2004
Response Authority:
CERCLA
Mob Date:
10/18/2004
Response Type:
Time-Critical
Demob Date:
 
NPL Status:
Non NPL
Completion Date:
 
Incident Category:
Removal Action
CERCLIS ID #:
NCN000407301
Contract #
RCRIS ID #:
 

Site Description

Please refer to Polrep 3 for background information.


Current Activities

During the reporting period, activities at 1145 Loflin Hill Road, Lot 6 included locating utilities by hand, digging around the base of the home and in a rock garden in the front yard, and excavation began in the backyard.  To date 8 trucks of contaminated soil have been loaded out.  Residents at Lot 6 began temporary relocation on December 1, 2004.
ERRS also began work to restore landscaping damaged at 1234 Loflin Hill Road due to heavy rains from 11/20-11/27 when site activities were shut down.  This damaged includes moderate trenching along the back of the property and severe trenching on the bank in front of the property.


Planned Removal Actions

The Removal Action at the 7* affected residences will involve a combination of excavation and capping with a barrier of clean soil of up to 2 feet and restoration.  Residents will be relocated while activities are conducted at their residence.
*Results of the August 2004 sampling event identified two more properties will arsenic levels above the Removal Action Level of 40 ppm.


Next Steps

Excavation will continue at 1145 Loflin Hill Road, followed by backfill and seeding.  The bank at the front of 1234 Loflin Hill Road will be hydro-seeded; the back of the property will be reseeded and retilled.


Key Issues

Rain and cold weather make it hard for the grass on the restored properties to grow, this will be a problem for all properties throughout the removal.
1145 Loflin Hill Road, Lot 6 must be completed by December 17, 2004 so that residents will be back in their home by the week of Christmas.


response.epa.gov/LoflinGoldMine