2.1.1 Narrative
On September 9, 2013, crews worked on backfilling excavation areas that have either been cleared by confirmation samples, or were excavated to the concrete foundation of the original building. START screened Grids 8 and 9 with an XRF, which indicated lead values >500ppm. Grids excavated an additional 6 inches. Crews also worked to cut large trees and pieces of timber into pieces small enough to dispose of.
On September 10, 2013, crews loaded trucks with remainder of Pile F for off site disposal. Crews also continued work on backfilling. Grids 8 and 9 were excavated until START XRF screening indicated lead values below 400. Confirmation samples were collected for Grids 8 and 9. Crews worked to excavate area in northeastern corner of site, along western edge of excavation pit. Soil is being staged in Pile G on eastern edge of site.
On September 11, 2013, crews removed protective steel sidewalk plates from site. Crews also worked to spread top soil over backfilled parts of site. OSC and START conducted XRF screening of temporary walkway between site and railway east of site, and found lead levels between 700-100ppm. 20 yards of mulch were dropped off and used to cover dirt pathway.
On September 12, 2013,crews loaded trucks with treated soil from pile G for off site disposal and used a hoe-ram to break up large pieces of concrete for disposal. Crews resumed backfilling and treating/excavating soil along eastern edge of site.
During all Site operations, START operated and maintained DataRam and Personal DataRam (pDR 1500) units to monitor all dust/particulates on and off Site. The personal data ram has been deployed to the cab of the excavator to monitor dust levels near on-site personnel. All personal data ram readings have been near or at back ground dust levels for the area (10-100 ug/m3). Average concentrations of dust have been 15-45 ug/m3. All site operations are being conducted using a water fog with a fire hose to minimize dust levels. The action level for nuisance dust is 500 ug/m3.
2.1.2 Response Actions to Date
US EPA's contractor Environmental Restoration is in the process of treating and excavating soil from 2 feet below ground surface to the original building's concrete foundation (approximately 5-5.5' below grade). Treated and excavated soil is being staged on the eastern edge of property for off-site disposal. Crews are then backfilling excavated areas with engineered sand. Top soil and seed will be graded on top of the sand fill to complete the site.
Samples collected from the treated soil and demolition debris were analyzed and results indicate that the constitutes of concern are under regulatory limits.
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
The owner of the property has been identified, but has been non- responsive to repeated attempts to arrange for access to the property.
The U.S. EPA has obtained a warrant from a U.S. Magistrate to conduct the Site Assessment and Emergency Removal Action.
U.S. EPA has recently identified that an investment firm, Sabre Investments LLC, has purchased the back taxes for the property but has not yet filed the deed.
|