United
States Environmental Protection Agency
Region X
POLLUTION REPORT
|
| Date: |
Wednesday, December 22, 2004
|
| From: |
Michael Szerlog
|
| To: |
NPFC Polreps, USCG (POLREP List)
|
Anthony Barber, EPA Region 10 (POLREP List)
|
|
Dan Opalski, EPA Region 10 (POLREP List)
|
Eugene Lee, EPA HQ (POLREP List)
|
|
Chris Field, Region 10 List - EPA Region 10
|
Steve Heaton, IDEQ - LUST Program
|
|
Wally Moon, EPA - UST Program
|
Miguel Bella, USCG
|
|
James Werntz, EPA
|
|
|
Subject:
|
Progress
Ashton Texaco Oil Release
363 Highway 20,
Ashton, ID
Latitude: 44.0750000 Longitude: -111.4600000
|
| POLREP No.: |
18
|
Site #:
|
Z0A3
|
| Reporting Period: |
11/1 to 11/30/04
|
D.O. #:
|
64-10-17
|
| Start Date: |
5/27/2003
|
Response Authority:
|
OPA
|
Mob Date: |
5/27/2003
|
Response Type:
|
|
| Demob Date: |
|
NPL Status:
|
Non NPL
|
| Completion Date: |
|
Incident Category:
|
Removal Action
|
| CERCLIS ID #: |
|
Contract #
|
|
| RCRIS ID #: |
IDR000201400
|
Reimbursable Account #
|
Z0A3
|
| FPN# |
E03012
|
|
|
November 1 through 7, 2004: ERRS Subcontracotr (1) ERRS Subcontractor conducted operations and maintenance activities. A total of 190 gallons of material recovered to date in the 1,000 gallon tank.
November 8 through 14, 2004: ERRS Subcontracotr (1) ERRS Subcontractor conducted operations and maintenance activities. A total of 190gallons of material recovered to date in the 1,000 gallon tank.
November 15 through 21, 2004: ERRS Subcontracotr (1) ERRS Subcontractor conducted operations and maintenance activities. A total of 190 gallons of material recovered to date in the 1,000 gallon tank.
November 22 through 30, 2004: ERRS Subcontracotr (1) ERRS Subcontractor conducted operations and maintenance activities. A total of 190 gallons of material recovered to date in the 1,000 gallon tank.
|
|
-Continue to recover oil. -In January/February time frame, install groundwater depression pumping system inside of the current extraction wells to increase the efficiency of oil removal.
|
|
-Transportation and Disposal of recovered product as needed. -EPA submitted an amended Oil Removal Project Plan to address the installation of groundwater depression pumping systems based upon the finding of oil in adjacent off site wells. This system will increase the efficiency of oil removal. -EPA will operate these systems for 6 months and then re-evaluate.
|
|
Amended Budget per USCG NPFC approval of amended Oil Removal Project Plan.
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| ERRS - Cleanup Contractor |
$300,000.00 |
$173,399.00 |
$126,601.00 |
42.20% |
| RST/START |
$130,000.00 |
$96,578.00 |
$33,422.00 |
25.71% |
| PRFA - IDEQ |
$20,000.00 |
$19,435.00 |
$565.00 |
2.83% |
|
Intramural Costs
|
| USEPA - Direct (Region, HQ) |
$45,000.00 |
$20,023.00 |
$24,977.00 |
55.50% |
| |
| Total Site Costs |
$495,000.00 |
$309,435.00 |
$185,565.00 |
37.49% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
response.epa.gov/AshtonTexaco
POLREP #18 Last Updated 12/22/2004
|