United States Environmental Protection Agency
Region III
POLLUTION REPORT



Date:
Wednesday, December 18, 2013
From:
Charlie Fitzsimmons, OSC

To:
Charlie Fitzsimmons, Region III, OPR
Linda Marzulli, Region III, OPR

Subject: 

Continuation of work
Sykesville Oil Spill
580 Obrect Rd, Sykesville, MD
Latitude: 39.3839000
Longitude: -76.9783000


POLREP No.:
62
Site #:
E043Z1
Reporting Period:
D.O. #:
Start Date:
 
Response Authority:
OPA
Mob Date:
 
Response Type:
Time-Critical
Demob Date:
 
NPL Status:
Non NPL
Completion Date:
 
Incident Category:
Removal Action
CERCLIS ID #:
Contract #
RCRIS ID #:
Reimbursable Account #
FPN#
E043Z1
 

Site Description

See previous POLREPS.


Current Activities

Closure activities were initiated the week of April 29, 2013. Soil stabilization and re-vegetation of disturbed areas, including any additional tree and shrub planting, required by Item 9.3 (h) of the EPA AOC is subject to the approval of the current property owner (Episcopal Ministries to the Aging, Inc. [EMA]).  It is anticipated that these activities will occur during the spring 2014 growing season to ensure establishment of healthy vegetation.

All monitoring wells, piezometers and sumps have been abandoned in accordance with the Code of Maryland Regulations (COMAR) resulting in the cessation of monitoring and product recovery.

No problems were encountered during this reporting period.


Planned Removal Actions

None planned.


Next Steps

Fogle's submitted a "Draft Seepage Area Closure Report" to EPA and MDE on December 13, 2013.  This document summarizes the activities taken by Fogle's relative to the removal of the sumps, piezometers and monitoring wells at the seepage area of the site.  It includes seven areas of concern all of which were completed, except for the revegation of area, which will occur in the spring of 2014.  This document will be reviewed by EPA and MDE.  

A final project report in accordance with section 9.11 of administrative order on consent is still pending.


Key Issues

MDE has agreed to continue oversight of the bioventing operation at the facility.  EPA activities will conclude after acceptance of project final report.


Estimated Costs *
  Budgeted Total To Date Remaining % Remaining
Extramural Costs
PRFA $640,000.00 $587,857.00 $52,143.00 8.15%
Intramural Costs
USEPA - Direct (Region, HQ) $30,000.00 $28,500.00 $1,500.00 5.00%
 
Total Site Costs $670,000.00 $616,357.00 $53,643.00 8.01%

* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.


response.epa.gov/sykesvilleoil

POLREP #62 Last Updated 12/18/2013