|
United
States Environmental Protection Agency
Region IV
POLLUTION REPORT
|
| Date: |
Tuesday, January 18, 2005
|
| From: |
Amy Feingold
|
|
Subject:
|
Loflin Gold Mine
Loflin Hill Road,
Trinity, NC
Latitude: 35.7250000 Longitude: -80.0433000
|
| POLREP No.: |
12
|
Site #:
|
A4AE
|
| Reporting Period: |
01/10/2005 - 01/15/2005
|
D.O. #:
|
|
| Start Date: |
10/19/2004
|
Response Authority:
|
CERCLA
|
Mob Date: |
10/18/2004
|
Response Type:
|
Time-Critical
|
| Demob Date: |
|
NPL Status:
|
Non NPL
|
| Completion Date: |
|
Incident Category:
|
Removal Action
|
| CERCLIS ID #: |
NCN000407301
|
Contract #
|
|
| RCRIS ID #: |
|
|
|
Please refer to Polrep 3 for background information.
|
|
During the reporting period, activities at 1265 Loflin Hill Road included continuation of excavation and hang digging around vegetation. ERRS received 5 loads of crush-n-run and created an area in the front of the property so that trucks would not block traffic on Loflin Hill Road during load out. To date, 33 trucks of contaminated soil have been sent off site to the Uwharrie Environmental Landfill in Mt. Gilead, NC.
|
|
The Removal Action at the 7* affected residences will involve a combination of excavation and capping with a barrier of clean soil of up to 2 feet and restoration. Residents will be relocated while activities are conducted at their residence. *Results of the August 2004 sampling event identified two more properties will arsenic levels above the Removal Action Level of 40 ppm.
|
|
Excavation will continue at 1265 Loflin Hill Road, followed by backfill and seeding. Due to weather conditions, some of the most recent areas seeded may have to be re-evaluated. The three remaining residences are being prioritized to determine the order in which they will be addressed.
|
|
No work took place on January 14, 2005 due to heavy rains the night prior. Rain and cold weather make it hard for the grass on the restored properties to grow; this will be a problem for all properties throughout the removal.
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| ERRS - Cleanup Contractor |
$1,300,000.00 |
$712,866.82 |
$587,133.18 |
45.16% |
| RST/START |
$96,000.00 |
$51,000.00 |
$45,000.00 |
46.88% |
|
Intramural Costs
|
| |
| Total Site Costs |
$1,396,000.00 |
$763,866.82 |
$632,133.18 |
45.28% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
response.epa.gov/LoflinGoldMine
POLREP #12 Last Updated 1/19/2005
|