Progress
Ashton Texaco Oil Release
363 Highway 20,
Ashton, ID
Latitude: 44.0750000 Longitude: -111.4600000
|
| POLREP No.: |
19
|
Site #:
|
Z0A3
|
| Reporting Period: |
12/1 to 12/31
|
D.O. #:
|
64-10-17
|
| Start Date: |
5/27/2003
|
Response Authority:
|
OPA
|
Mob Date: |
5/27/2003
|
Response Type:
|
Emergency
|
| Demob Date: |
|
NPL Status:
|
Non NPL
|
| Completion Date: |
|
Incident Category:
|
Removal Action
|
| CERCLIS ID #: |
|
Contract #
|
|
| RCRIS ID #: |
IDR000201400
|
Reimbursable Account #
|
Z0A3
|
| FPN# |
E03012
|
|
|
December 1 through 5, 2004: ERRS Subcontracotr (1) ERRS Subcontractor conducted operations and maintenance activities. A total of 191 gallons of material recovered to date in the 1,000 gallon tank.
December 6 through 12, 2004: ERRS Subcontracotr (1) ERRS Subcontractor conducted operations and maintenance activities. A total of 191 gallons of material recovered to date in the 1,000 gallon tank.
December 13 through 19, 2004: ERRS Subcontracotr (1) ERRS Subcontractor conducted operations and maintenance activities. A total of 191 gallons of material recovered to date in the 1,000 gallon tank.
December 20 through 26, 2004: ERRS Subcontracotr (1) ERRS Subcontractor conducted operations and maintenance activities. A total of 191 gallons of material recovered to date in the 1,000 gallon tank.
December 27 through 31, 2004: ERRS Subcontracotr (1) ERRS Subcontractor conducted operations and maintenance activities. A total of 192 gallons of material recovered to date in the 1,000 gallon tank.
|
|
-Continue to recover oil. -During the week of February 14th 2005, EPA plans to install a groundwater depression pumping system inside of the current extraction wells to increase the efficiency of oil removal. The pumping system will continuously pump groundwater from the three on site extraction wells, treat the groundwater, and then discharge it (under permit) to the city of Ashton's POTW.
|
|
-Transportation and Disposal of recovered product as needed. -Amended Oil Removal Project Plan to address the installation of groundwater depression pumping systems was approved by USCG NPFC for funding. -EPA to mobilize week of February 14, 2005 to install pumping system. -EPA will operate these systems for another 6 months and then re-evaluate.
|
|
New Budget listed below - USCG NPFC approval of amended Oil Removal Project Plan.
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| ERRS - Cleanup Contractor |
$300,000.00 |
$175,496.00 |
$124,504.00 |
41.50% |
| RST/START |
$130,000.00 |
$97,692.00 |
$32,308.00 |
24.85% |
| PRFA - IDEQ |
$20,000.00 |
$19,435.00 |
$565.00 |
2.83% |
|
Intramural Costs
|
| USEPA - Direct (Region, HQ) |
$45,000.00 |
$20,023.00 |
$24,977.00 |
55.50% |
| |
| Total Site Costs |
$495,000.00 |
$312,646.00 |
$182,354.00 |
36.84% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
response.epa.gov/AshtonTexaco
POLREP #19 Last Updated 1/31/2005
|