United States Environmental Protection Agency
Region IV
POLLUTION REPORT



Date:
Monday, February 7, 2005
From:
Amy Feingold


Subject: 

Loflin Gold Mine
Loflin Hill Road, Trinity, NC
Latitude: 35.7250000
Longitude: -80.0433000


POLREP No.:
15
Site #:
A4AE
Reporting Period:
01/31/2005 - 02/05/2005
D.O. #:
Start Date:
10/19/2004
Response Authority:
CERCLA
Mob Date:
10/18/2004
Response Type:
Time-Critical
Demob Date:
 
NPL Status:
Non NPL
Completion Date:
 
Incident Category:
Removal Action
CERCLIS ID #:
NCN000407301
Contract #
RCRIS ID #:
 

Site Description

Please refer to Polrep 3 for background information.


Current Activities

During the reporting period, activities at 1265 Loflin Hill Road included final grading, restoration of walkway and driveway, placement of mulch in flowerbeds and other minor tasks to complete the yard.  To date, 113 trucks of contaminated soil have been sent off site to the Uwharrie Environmental Landfill in Mt. Gilead, NC. Also, 195 loads of clean backfill and 75 loads of topsoil have been brought to the property.
Activities at 989 Loflin Hill Road, Lot 15 included locating of utilities and digging around the base of the trailer by hand, as well as, the placement of silt fencing.


Planned Removal Actions

The Removal Action at the 7* affected residences will involve a combination of excavation and capping with a barrier of clean soil of up to 2 feet and restoration.  Residents will be relocated while activities are conducted at their residence.
*Results of the August 2004 sampling event identified two more properties will arsenic levels above the Removal Action Level of 40 ppm.


Next Steps

The only activity remaining at 1265 Loflin Hill Road is landscaping.
The next steps at 989 Loflin Hill Road, Lot 15 include excavation and load out.  Residents in this property will not participate in temporary relocation because they will already be out of their home for the duration of the removal for other reasons.
Due to weather conditions, some of the most recent areas seeded may have to be re-evaluated.


Key Issues

Work was stopped at 10:30 am on February 3, 2005 due to heavy rain.
Rain and cold weather make it hard for the grass on the restored properties to grow; this will be a problem for all properties throughout the removal.


response.epa.gov/LoflinGoldMine