2.1.1 Narrative
MONDAY December 1, 2014: Personnel on-site: EPA – 1, ERRS – 4. OSC Reiner mobilized to site. ERRS Chernick and crew, including 2 APEC subcontract staff, mobilized to site. Initial health and safety discussion held. OSC visited Marpi landfill to assess location where treated soils will be stored. ERRS began removing geotextile cover from biotreatment cells and stacking soil in preparation for loading into trucks.
TUESDAY December 2, 2014: Personnel on-site: EPA – 1, ERRS – 4. ERRS began loading treated soil from biotreatment cells into trucks for transport to Marpi landfill, where it will be used as daily cover. 33 truckloads of treated soil were taken to Marpi.
WEDNESDAY December 3, 2014: Personnel on-site: EPA – 1, ERRS – 4. ERRS continued transporting treated soil to Marpi landfill. 28 truckloads of treated soil were taken to Marpi. ERRS worked on removing old, degraded collection lines from oil skimming pumps in collection sumps, in order to replace them with new lines.
THURSDAY December 4, 2014: Personnel on-site: EPA – 1, ERRS – 4. 30 truckloads of treated soil were taken to Marpi landfill. ERRS began set-up of a new sock filter system on the wastewater treatment system used to treat water from the collection sumps.
FRIDAY December 5, 2014: Personnel on-site: EPA – 1, ERRS – 4. 32 truckloads of treated soil were taken to Marpi landfill. ERRS completed installation of sock filter system on the wastewater treatment system and general system maintenance.
SATURDAY December 6, 2014: Personnel on-site: EPA – 1, ERRS – 2. 18 truckloads of treated soil were taken to Marpi landfill. Mechanical issues with two of the four haul trucks made one unavailable all day and the other only available a part of the day.
MONDAY December 8, 2014: Personnel on-site: EPA – 1, ERRS – 4. 25 truckloads of treated soil were taken to Marpi landfill. Continued mechanical issues made only three haul trucks available today. OSC Reiner and ERRS inspected all sumps in the interceptor and barrier trenches installed previously on the site. For the most part, the sumps showed little to no sheen.
TUESDAY December 9, 2014: Personnel on-site: EPA – 1, ERRS – 4. 4 truckloads of treated soil were taken to Marpi landfill. Mechanical issues with trucks continued today, with only one haul truck available. Nevertheless, hauling of the last load of treated soil was completed today. ERRS crew assessed damaged spots of biocell liner and applied patches to four sections ranging from 2’ to 12’ across. OSC Reiner and ERRS dug test pits in two locations: immediately outside the PP1&2 fence adjacent to the drum storage containment area and in the old leach field by the oil/water separator at Tank 104. A very faint sheen was detected in the first location, but that may have been due to hydraulic oil on the backhoe arm. A more distinct and lasting sheen, with evident rainbow coloration, was detected on the surface of groundwater at the second location, by Tank 104.
WEDNESDAY December 10, 2014: Personnel on-site: EPA – 1, ERRS – 3. OSC Reiner collected influent and effluent samples from the wastewater treatment system and shipped them to the lab for analysis. ERRS conducted a detailed inventory of EPA supplies stored in two shipping containers on the PP1&2 site, to be used in planning the next phase of work.
THURSDAY December 11, 2014: Personnel on-site: EPA – 1, ERRS – 2. EPA and ERRS demobilized from site.
2.1.2 Response Actions to Date
See above and previous polreps
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
CNMI Commonwealth Utilities Corporation
2.1.4 Progress Metrics
| Waste Stream |
Medium |
Quantity |
Manifest # |
Treatment |
Disposal |
| petroleum contaminated soil |
soil |
2000 cu yds |
|
|
used as daily cover at Marpi landfill |
| |
|
|
|
|
|
| |
|
|
|
|
|
|