U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
ASIG Sand Island - Removal Polrep

EPA Emergency Response

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region IX

Subject: POLREP #7
ASIG Sand Island

Honolulu, HI
Latitude: 21.3168235 Longitude: -157.8900084


To:
From: Donn Zuroski, OSC
Date: 2/22/2015
Reporting Period: 2/15/15 - 2/22/15

1. Introduction
  1.1 Background
   
Site Number: Z9EA    Contract Number:  
D.O. Number:      Action Memo Date:  
Response Authority: OPA    Response Type: Emergency
Response Lead: EPA    Incident Category: Removal Action
NPL Status:    Operable Unit:
Mobilization Date: 1/25/2015    Start Date: 1/25/2015
Demob Date:      Completion Date:  
CERCLIS ID:    RCRIS ID:
ERNS No.:    State Notification:
FPN#: E15901    Reimbursable Account #:

1.1.1 Incident Category
OPA Response


1.1.2 Site Description

The site includes the area in and adjacent to the tank farm that supplies fuel to the Honolulu International Airport.  This tank farm facility includes 16 above ground storage tanks (used to store Jet a fuel) and pipelines to receive product form the Kapolei Refinery (located in Campbell Industrial Park) or product directly from oil tankers in Honolulu Harbor, as well as pipelines running form the tank farm directly to the airport.  The tank farm sits on land owned by the State of Hawaii Department of Transportation Airports Division.  The tanks, piping, structures and associated equipment are owned by Hawaii Fueling Facilities Corporation a consortium of (22?) airlines.  The facility is operated by aircraft Service International group (ASIG).

1.1.2.1 Location
The tank farm is situated on the main road between Honolulu and Sand Island.  Honolulu Harbor and Ke'ehi Lagoon are both in near proximity.  A smaller tank farm operated by Hawaiian Independent Energy Co. is located adjacent to the South. 

1.1.2.2 Description of Threat
On December 22, 2014,  the staff at the ASIG tank farm noted a substantial shortage in the inventory of Tank #2.  The storage capacity of tank #2 is approximately 2.8 million gallons.  Over the course of the next month, ASIG conducted a series of tests and an internal investigation of the tank. This included transfer of the jet fuel to the airport tank farm, venting and cleaning the tank in question, locating the area of concern on the tank bottom, and cut out of a coupon on the floor.  Once the coupon was removed ASIG found that the area below the tank was saturated with fuel. They then notified the NRC and the HI DOH HEER office that they had a release of 1000 bbls of Jet fuel (42,000 gallons) at their facility.

1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results
Upon notification from ASIG (January 22, 2015) the HI DOH Hazard Evaluation and Emergency Response Office (HEER) deployed one of the State On-Scene Coordinators (SOSC) to the facility.   The SOSC evaluated the situation on site and immediately notified the EPA Region 9 duty officer.


2. Current Activities
  2.1 Operations Section
    2.1.1 Narrative
This facility is adjacent to both Honolulu Harbor and Ke'ehi Lagoon, and has a history of tank releases.  The tank farm contains 16 ASTs with a combined capacity to hold 44 million gallons of fuel.  Although the facility is surrounded along the perimeter by a concrete wall, the area around the tanks is not paved or sealed from downward migration of fuel should it get out of the tanks. The soil underlying the tanks is sand with layers of crushed coral and fill material.  The water table beneath the facility is tidally influenced.   In 1996, there was a sizable tank release inside the facility.  In 2008, there was (another) release from piping/appurtanances related to a tank or tank, again inside the facility. As a result of the 2008, event the facility owners installed a bentonite slurry barrier wall along 3,000 linear feet of the perimeter. 

According to the engineering firm that installed the barrier wall, "this barrier system will last for centuries".  However, a substantial amount of jet fuel has escaped the slurry wall and has been found (on the water table) outside the tank farm, within 50 yards of Ke'ehi Marina.

At present, the Jet fuel is being pumped from four extraction trenches and a few wells inside the tank farm, and several locations outside the tank farm, directly into vac trucks.  The vac truck loads are taken offsite for processing at the Honolulu Airport fuel storage farm.  An average of 1,000 gallons of pure jet fuel per day have been recovered.   

2.1.2 Response Actions to Date
ERT, the (EPA) FOSC, the SOSC, and the RP have established a nimble and effective Unified Command approach to issue shaping and problem solving. ERT and the OSC are closely observing and directing the placement and construction of extraction trenches/wells /pits/sumps.  As a result of the (Unified Command) collaborative approach to solving technical problems, the design and installation of the capture and extraction system and monitoring wells is revised and refined daily.  Furthermore, there are few surprises or unavoidable delays.

Numerous exploratory trenches and bore holes, as well as four extraction trenches and several extraction and monitoring wells have been installed inside the tank farm.   More than fifty exploratory bore holes, multiple monitoring wells and several extraction sump/wells have been installed outside the tank farm.  In order to ensure that no possible path for the jet fuel to reach the water is unattended, the RP has installed boom along the water's edge in the area of concern and is monitoring it closely for evidence of any releases.

At the end of each day the Unified Command holds a debrief and has a "brainstorming" session to develop the path forward for the next day's effort.  Careful attention is being paid to ensure that the emergency response (short-term) actions are consistent with the long-term remedy.  .

Development of a strategy to capture the fuel, and the design of an interceptor trench to insure that the jet fuel plume does not reach the water's edge, are completed.

2/16/15
One ERT, FOSC and four START are on site.  FOSC conducts the morning safety briefing along with the RP response contractor. Capture and removal of jet fuel both inside and outside the tank farm continues. Visual monitoring of the boom continues. Additional extraction and monitoring wells are installed. New ERT person is introduced. FOSC requests RP to provide well survey and tidal survey for the site.

2/17/15
ERT person and four START personnel are on site. ERT, RP and RP response contractor conduct safety briefing and work scheduled for the day. Geoprobe on site to install additional monitoring wells. Capture and
removal of jet fuel both inside and outside the tank farm continues. Visual monitoring of the boom continues.

2/18/15
ERT and four START personnel are on site. ERT, RP and RP response contractor conduct safety briefing and
provide today's work schedule. RP contractor on site to begin installing pumping system with skimmers.
Waste disposal plan expected today from RP. Geoprobe team will continue to complete wells and develop
them.  Continued visual monitoring of boom. 

2/19/15
ERT and four START personnel are on site. ERT, RP and RP response contractor conduct safety briefing.
Work schedule provided. Well development is on-going. Visual monitoring and change out of sorbents in the
boomed area. Extraction wells continue to be pumped by the vac trucks. 
 
2/20/15 
ERT and four START personnel are on site. ERT, RP and RP response contractor conduct safety briefing.
START's two teams continue to gauge wells prior to 8am safety meeting.  Vac trucks working inside and outside pumping extraction/recovery wells.  3 sumps installed, 2 adjacent to tank#2 and one on outside of slurry wall.
RP has provided UIC permit and other information relating to the disposal of contaminated water generated
during the oil recovery process. Visual monitoring of the boom continues.

2/21/15
ERT and two START personnel are on site. ERT and RP response contractor conduct safety briefing. Minimal
activity on site today.  Electrician wiring pumping control box and one vac truck is working outside. Sunday
will be used as an 'extended rebound' period for the oil in monitoring and extraction/recovery wells.
Full site activity resumes on Monday Febuary 23th. Visual monitoring of the boom continues. 


2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
Verbal Notice of Federal Interest was given by the OSC on his arrival at the site.  The hard copy of the NOFI was hand delivered on 1/27/15.  A CWA 311(c) order was issued and hand delivered by the OSC on 1/30/15.   Further Federal enforcement actions are TBD.

2.1.4 Progress Metrics
Estimates of recovered jet fuel have been revised downward due the continued dewatering of the extracted liquid.


Waste Stream Medium Quantity Manifest # Treatment Disposal
 jet fuel  pure   approx.22,000g    oi/water sep  re-use
           
           


  2.2 Planning Section
    2.2.1 Anticipated Activities
The initial approach has been to aggressively extract the jet fuel, to define the extent of the subsurface release, and to design and install engineered capture and monitoring systems to be operated over the long term. 

ASIG has installed four extraction trenches, and multiple extraction wells and sumps inside the tank farm,  several extraction sump/wells outside the tank farm, and has continued aggressive removal of the jet fuel from these engineered systems.
 
The extent of the subsurface plume is still under study, but enough information has been collected to initiate recovery from sump/wells installed outside the tank farm.

The extraction wells and trenches inside the tank farm are completed.  The infrastructure to utilize an automatic pumping system in the trenches is under construction.  In the interim, vac trucks are used to remove the jet fuel that has been captured in the trenches. 

The construction of the system to extract the fuel outside the tank farm is underway.  At present, vac trucks are utilized to remove jet fuel from bore holes and the sump/well system outside the tank farm.

An interceptor trench is under design and will be installed the full length of the area of concern between the extraction trenches and the water front.

2.2.1.1 Planned Response Activities
Contain the release. Complete installation of systems both inside and outside the tank farm to capture and remove the jet fuel.  Construct a permanent interceptor trench to ensure that the fuel is kept from reaching the marina. Develop and implement a long term recovery and monitoring plan.

2.2.1.2 Next Steps

Further refine the long-term strategy.

2.2.2 Issues
TBD

  2.3 Logistics Section
    No information available at this time.

  2.4 Finance Section
    No information available at this time.

  2.5 Other Command Staff
    No information available at this time.

3. Participating Entities
  3.1 Unified Command
EPA
HI DOH
ASIG

3.2 Cooperating Agencies
USCG Sector Honolulu
HI HEER Office
HI DOH
HI DLNR
HFD

4. Personnel On Site
  No information available at this time.

5. Definition of Terms
  No information available at this time.

6. Additional sources of information
  No information available at this time.

7. Situational Reference Materials
  No information available at this time.