United
States Environmental Protection Agency
Region IV
POLLUTION REPORT
|
| Date: |
Thursday, March 24, 2005
|
| From: |
Amy Feingold
|
|
Subject:
|
Loflin Gold Mine
Loflin Hill Road,
Trinity, NC
Latitude: 35.7250000 Longitude: -80.0433000
|
| POLREP No.: |
20
|
Site #:
|
A4AE
|
| Reporting Period: |
03/07/2005 - 03/14/2005
|
D.O. #:
|
|
| Start Date: |
10/19/2004
|
Response Authority:
|
CERCLA
|
Mob Date: |
10/18/2004
|
Response Type:
|
Time-Critical
|
| Demob Date: |
3/14/2005
|
NPL Status:
|
Non NPL
|
| Completion Date: |
|
Incident Category:
|
Removal Action
|
| CERCLIS ID #: |
NCN000407301
|
Contract #
|
|
| RCRIS ID #: |
|
|
|
Please refer to Polrep 3 for background information.
|
|
During the reporting period, activities at 964 Loflin Hill Road, Lot 55 included load out of contaminated soil, placement of backfill and topsoil and landscaping. To date, 11 loads of backfill and 5 loads of topsoil have been placed on the property. Seven loads of contaminated soil have been sent to the Uwharrie Environmental Landfill in Mt. Gilead, NC. Residents ended temporary relocation on March 11, 2004. This property has been completed. Activities at 1234 Loflin Hill Road included hydroseeding of the front bank and areas that had been washed out on the south and east part of the property. Minor washouts were raked, seeded and strawed at 1241 Loflin Hill Road and 989 Loflin Hill Road, Lot 6. All staff and equipment has been demobalized from the Site.
|
|
All of the field work for this Site has been completed.
|
|
At some point in the near future ERRS and/or START will have to return to the Site to document how well the grass is growing and if additional landscaping is needed.
|
|
Site work was canceled on Tuesday, March 8, 2005 due to rain. The Removal Action at the Site has been completed; many of the lawns are still trying to establish grass and will have to be monitored periodically after demobilization.
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| ERRS - Cleanup Contractor |
$1,650,000.00 |
$1,169,205.00 |
$480,795.00 |
29.14% |
| RST/START |
$135,000.00 |
$89,822.00 |
$45,178.00 |
33.47% |
|
Intramural Costs
|
| |
| Total Site Costs |
$1,785,000.00 |
$1,259,027.00 |
$525,973.00 |
29.47% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
response.epa.gov/LoflinGoldMine
POLREP #20 Last Updated 3/24/2005
|