2.1.1 Narrative
At this time, an abandoned oil/gas well has been identified under the structure, the pipe from the culvert has been determined to originate from the area of the subject well. Oil has been found migrating within and alongside the pipe between the well and the culvert. EPA initiated actions intending to reduce the ability for oil to migrate to the water. EPA directed its contractor to remove oil and debris from the well (using hand methods) to an attainable depth and to place cement into the well. However, it appears that the attempt may not have been successful and may have increased the migration of oil into Stackyard Run without stopping the flow of gas to the surface of the well.
2.1.2 Response Actions to Date
See Prior POLREPs for activities through September 10, 2015.
In July 2015, EPA and its contractors attempted to remove oil and debris from the well using hand drilling methods and a high power vacuum truck in hopes of finding a shallow blockage. Concrete and brick debris along with rock were removed from the well. Operations could not initially advance past approximately 50 feet due to caving sidewalls.
In August 2015, EPA and its contractors attempted to clean the well to a deeper level by installing temporary PVC casing and using a water drill in addition to raising and lowering a bit by hand. These methods, along with a vacuum truck, resulted in removal of additional oil and debris to deepen the well to about 70 feet. Afterwards, the EPA contractor mixed sand and cement and poured the mixture into the wellbore using 5 gallon buckets while pulling the temporary casing. At the conclusion of this process, gas was observed bubbling to the surface through the just-placed column of the cement/sand mixture.
In September 2015, EPA and its contractors attempted to remove some of the cement from the wellbore and effect a tighter seal at the surface of the wellbore and minimize the migration of gas. A steel cap was welded in the wellbore with a nipple to allow the gas to be directed into a pipe and outside the structure. During this activity, the cement was found to not have hardened.
The OSC conducted monitoring of the well and inside the unit for LEL and VOCs utilizing a five gas
Multi Rae meter. Monitoring was conducted 1 to 2 times a week through the beginning of October. Readings measured 0%
LEL and VOCs ranged from 0 to 2.5 ppm within the unit. There were no LEL or VOC readings detected outside the unit. Weekly air monitoring was suspended after the results showed that the migration of gas is being contained by the welded cap and passive venting system to the outside. The OSC would conduct periodic air monitoring if deemed necessary. The OSC conducted monitoring the week of
November 23, 2015 and confirmed that levels remain at 0% LEL and VOCs at 1.4
ppm.
The OSC and Property owner discussed the possible need for a vapor mitigation system should the removal activity result in a reduction of oil discharging to Stackyard Run. The OSC requested the owner not move forward with such construction pending observations and monitoring.
Beginning in September 2015, the OSC began periodic observations of the amount of oil on Stackyard Run to determine if the efforts of the removal action have resulted in a reduction of the amount of oil discharging into the flowing waters of Stackyard Run.
Observations in September showed a heavy silver and rainbow sheen coming out of the culvert during every monitoring event. A large amount of brown mousse-like oil was collected by the boom and subsequently removed by absorbent pads when possible. Overall observations for September showed an increase in oil on Stackyard Run after the completion of the removal activities completed in August. Monitoring of Stackyard Run during October continued to show a silver and rainbow sheen but not on a continual basis. Brown oil continued to collect at the boom area. The amount of oil had decreased since the monitoring in September but overall there appears to be more oil than before the capping activities.
EPA continues to await for information relating to the disposal of oil and oil-contaminated debris resulting from the removal activities in August.
On November 3, 2015, the OSC evaluated the area of oil discharge in the culvert adjacent to the well. Oil was still observed seeping through the wall, although such seepage seemed to have slowed. However, oil droplets and blobs were observed coming up through cracks in the floor of the culvert directly into the waters of Stackyard Run. The discharge of oil appears to have increased from periods prior to removal activities intended to reduce the discharge. The OSC will continue to assess this situation.
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
See Prior POLREPs.
2.1.4 Progress Metrics
Waste Stream |
Medium |
Quantity |
Manifest # |
Treatment |
Disposal |
oil |
solids |
4 - 55-gallon drums |
|
|
X |
oil |
oily liquids |
3100 gallons |
|
|
X |
oil |
oil solids |
2 tons |
|
|
X |
|