Summary from 1100 Planning Meeting:
Participants discussed roles during the removal action: Environmental Issues: DEQ and USEPA will coordinate efforts to ensure that environmental concerns are addressed during all of the removal activies taking place on site.
Oregon Bureau of Environmenal Services will ensure that all site waters are disposed of properly and meet the necessary permit requirements. If water contaminats exceed applicable discharge permit values the waste water may be disposed of as process waste water at a local oil recycling facility.
OR OSHA: will be conducting an investigation into the cause of the accident.
Tim Archer with NRC gave an operations debrief for the operational period 0415 to 2000 (May 9,2005).
On Site activities completed included: -Five, 20K baker tanks have been filled with site contact waters. -Building 4 has had the liquids from the floor pumped into an aboveground poly tank. -The Baker tanks and poly tank were sampled today for disposal purposes.
Off Site water activities included: -changing out the sweep boom
Air monitoring activities are being conducted by Marine Environmental.
Incident Investigation is being conducted by OR OSHA. Six of eight buildings have been turned over to Lacamas Labs. The remaining 3 buildings still need to be inspected. OR OSHA and Insurance company representatives will be working together to coordinate collection of evidence.
The following staff were in attendance for the 1100 meeting: Craig T Cristy, Structural Eng for RP Marc Callaghan, FOSC, USEPA Jennifer Powell, RPOS Greg Marhett, Schaffer Engineering, Insurance Martin Stapelson, Shcaffer Engineering, Insurance Mike Amen, Site Safety Officer, NRCS Brian Williams, Site Safety Officer, Marine Environmental Jason Davendonis, Shaw, Insurance Mike Kratovil, Lacmas Labs Peter Titteringtor, Lacamas Labs Tim Dean, OR Bureau of Env Services Allen Erickson, Owner Lacamas Labs Erin Lynch, EPA-Ecology and Environment Tim Archer, NRCS, Removal Manager Penny Wolfe McCormick, Oregon OSHA Jason Potts, NRCS
|