|
United
States Environmental Protection Agency
Region I
POLLUTION REPORT
|
| Date: |
Friday, May 13, 2005
|
| From: |
Frank Gardner
|
|
Subject:
|
InterRoyal Fire
Reservoir Avenue,
Plainfield, CT
Latitude: 41.6775000 Longitude: -71.9203000
|
| POLREP No.: |
12
|
Site #:
|
012U
|
| Reporting Period: |
May 10-12, 2005
|
D.O. #:
|
37
|
| Start Date: |
4/26/2005
|
Response Authority:
|
CERCLA
|
Mob Date: |
4/26/2005
|
Response Type:
|
Emergency
|
| Demob Date: |
|
NPL Status:
|
Non NPL
|
| Completion Date: |
|
Incident Category:
|
Removal Action
|
| CERCLIS ID #: |
CTD045110913
|
Contract #
|
68-W-03-037
|
| RCRIS ID #: |
CTD045110913
|
|
|
The Inter Royal Site was the location of a large (over 1,000,000 square feet) abandoned mill structure located in the center of Plainfield, Connecticut. Originally constructed as a textile mill in approximately 1906, Inter Royal manufactured office and hospital furniture from the mid-1950s until 1985. Since that time, the Site has been abandoned, except for a plastic recycling operation in a portion of the building in 1991/1992.
On Tuesday, April 26, 2005 a fire destroyed the northern third of the mill, which was comprised primarily of a three-story brick and timber structure. Other ancillary structures in this northern portion include the boiler room, smokestack, and water tower. The southern 2/3 of the Site includes a sprawling single-story mill structure, which was not damaged by the fire but is in an advanced state of decay and was partially demolished approximately five years ago. See previous polreps for additional background information.
As a result of the fire, potentially-asbestos-contaminated fire debris was deposited over an area measuring approximately five miles long by one-half mile wide. Based on funding limitations and the magnitude of the problem, DEP requested that EPA take over the cleanup of this debris field. Based on this request, discussions with local, state, and federal health agencies, and the presence of friable asbestos-containing material on residential properties, EPA’s Superfund Removal Program initiated an emergency removal action on the morning of Thursday, 28 April 2005.
|
|
EPA continues to direct emergency response activities utilizing the Incident Command System with the support of DEP and local authorities. The incident command post has been largely relocated to a meeting room in the Plainfield Town Hall. However, the mobile command post is still being used to provide critical workstations and field communications capabilities.
Cleanup activities in the debris field area are now complete as of May 12, 2005. Crews cleaned up debris on 681 affected residential properties as well as several agricultural properties. Crews also cleaned up debris from active railroad lines and fields and open spaces accessible to the public.
The ERRS contractor is currently mobilizing equipment and preparing for demolition of unstable structures within the fire-damaged area, so that critical sampling activities can be safely conducted within that area.
|
|
The ERRS contractor is preparing to begin the above-referenced demolition work during the week of May 16, 2005. After the demolition activities are complete, sampling crews will be able to safely enter the area for the purpopse of determining whether contaminated debris, rubble, and/or firefighting water may be present within the footprint of the structure.
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| ERRS - Cleanup Contractor |
$750,000.00 |
$620,000.00 |
$130,000.00 |
17.33% |
| RST/START |
$400,000.00 |
$154,000.00 |
$246,000.00 |
61.50% |
|
Intramural Costs
|
| USEPA - Direct (Region, HQ) |
$200,000.00 |
$50,000.00 |
$150,000.00 |
75.00% |
| |
| Total Site Costs |
$1,350,000.00 |
$824,000.00 |
$526,000.00 |
38.96% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
response.epa.gov/interroyalfire
POLREP #12 Last Updated 5/13/2005
|