Site Number: |
C5N8 OU1 |
|
Contract Number: |
|
D.O. Number: |
|
|
Action Memo Date: |
6/22/2015 |
Response Authority: |
CERCLA |
|
Response Type: |
Time-Critical |
Response Lead: |
PRP |
|
Incident Category: |
Removal Action |
NPL Status: |
Non NPL |
|
Operable Unit: |
1 |
Mobilization Date: |
11/16/2015 |
|
Start Date: |
11/16/2015 |
Demob Date: |
|
|
Completion Date: |
|
CERCLIS ID: |
|
|
RCRIS ID: |
|
ERNS No.: |
|
|
State Notification: |
|
FPN#: |
|
|
Reimbursable Account #: |
|
1.1.1 Incident Category
Time Critical Removal Action
1.1.2 Site Description
The
Site consists of an alley (owned by the City of Chicago) and a railroad spur
(historically operated by Burlington Northern Santa Fe Railway [BNSF]) located
in the Lower West Side (Pilsen) area of Chicago, Cook County. The Site is in the City’s
25th Ward. The east to west portion of the
alley is approximately 460 feet (ft) long and 18 ft wide (approximately 8,280
square feet [ft2] in area) and is roughly paved with asphalt over
25% of its length from the east side. The north to south portion of the alley is
about 110 feet long. The remaining 75%
of the alley is soil. The alley connects South Loomis Street and South Throop Street and is south of West 21st
Street and north of West Cermak Road. The
alley is bordered to the north by H. Kramer and Company (H. Kramer) and Co., the east
by South Throop Street, to the south by commercial and industrial businesses,
and to the west by the railroad spur and then South Loomis Street.
The railroad spur is approximately 1,120 ft
long and 28,215 ft2 in total area. The railroad spur consists of an unused rail
track and soil
and asphalt where it is bisected by South Loomis Street. The
western portion of the railroad spur is located in the north region of a
property occupied by the Benito Juarez Community Academy (Juarez), located at
1450-1510 West Cermak Road. The railroad spur curves to the
south, crosses South Loomis Street, and extends along the west boundary of H.
Kramer, located at 1345 West 21st Street. The eastern portion of the
railroad spur is bordered by businesses along Loomis Street and West Cermak
Road to the south. According to a historical Sanborn fire insurance map, the
railroad spur and the alley have existed since at least 1914.
The alley and railroad spur soil (surface soil and subsurface soil) generally consists of silty, clayey, sandy, and gravelly fill materials. In the alley soil, some traces of wood chips, cinders, pieces of glass, brick, plastic debris, and slag were observed [slag was observed in eight alley soil borings and one railroad spur soil boring]. Slag is a solid-phase waste generated by secondary lead processing. In general, the surface and subsurface railroad soil contained more gravel than the alley soil. The western portion of the railroad spur west of Loomis street also contained vegetation (weeds) and garbage.
These aforementioned areas have been divided into 10 Areas as shown below (Please note that Area 1 east is the portion directly north of the baseball field.) :
1.1.2.1 Location
In addition to the information provided in the previous section. The geographical coordinates for the alley portion of the Site are 41° 51'
10.38" North latitude and 87° 39' 35.54" West longitude. The geographical coordinates for the railroad
portion of the Site are 41° 51' 13.58" North latitude and 87° 39'
41.66" West longitude. The Site is an industrial site in a residential neighborhood with a
portion of it (Western Area of the Railroad Spur west of Loomis Street) located
within a ¼-mile of two schools - Juarez and the Manuel Perez Jr. Elementary
School (Perez). Two City of Chicago
parks are located within a ½-mile-radius of the Site, Dvorak Park and Throop
Park.
1.1.2.2 Description of Threat
EPA Removal Site Assessment
analytical results document high levels of Lead in soil at or near the surface (which exceed the EPA Removal Management Level [RML] of 800 mg/kg for industrial use scenario). Access to the Alley is unrestricted and the fence in portions of the railroad spur is inadequate to prevent trespassers. The surface soil at the Site has the potential to migrate offsite via wind, rain, vehicular and
pedestrian traffic, or manual dispersion and presents a threat of exposure to the residents and workers in the surrounding area.
1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results
EPA conducted a removal site assessment from Dec. 2012 to 2013 in the field and found that average alley surface soil total lead was 2419 mg/kg. Average railroad spur surface soil total lead was 4340 mg/kg. In addition to the high concentrations of total lead, two soil samples from the alley and one from the railroad spur collected from 0 to 6 inches bgs contained TCLP lead at concentrations exceeding the TCLP lead regulatory limit of 5.0 mg/L in 40 C.F.R. § 261.24(b).
|
|
|
2.1.1 Narrative
Responsible Parties initiated
the cleanup at the Site on 11/16/2015. EPA OSC and EPA START oversaw the cleanup
onsite. The overall goal of the removal action is to remove
the threat of lead exposure to surrounding residents and workers from surface
soil through: 1) removal of soil contaminated with high levels of lead above
the EPA RML, and 2) placement of permanent covers at the Site.
2.1.2 Response Actions
to Date
A. Response actions taken from 11/16 to 12/30/2015 are documented (with detail) in the previous POLREPS #1,2,3,4, & 5. To summarize, during the aforementioned period, high levels of lead contaminated soil (above the hazardous waste characteristic) were excavated, treated (to non-hazardous waste) and disposed offsite at a permitted landfill in Areas 4 and 8. In addition, low levels of lead contaminated soil (non-hazardous) were excavated and disposed offsite at a permitted landfill. Solid waste, vegetation, most rail ties and rail were also removed. All areas were graded with gravel cover with an underlying geotextile fabric for preparation for asphalt, except for Area 1 west where a final gravel cover was completed. Since the Asphalt plants closed in November, work crews temporarily demobed on 12/30/2015, with plans to return in April 2016.
B. The following response actions were taken from April 1 to July 6, 2016:
4/1/2016 - H.Kramer contractors met with Chicago DOT (CDOT) officials to review the scope of the grading and paving work for Areas 5,7,8, &9 (areas to be paved by the City DOT).
4/11/2016 - H Kramer met with BNSF representatives and contractors and the remaining railroad ties where removed on April 25.
5/3 to 5/5/2016 - CDOT crews completed final grading of Areas 7,8, and 9.
5/20/2016 CDOT crews completed final asphalt paving work in Areas 7,8, and 9.
5/26 to 5/27/2016 CDOT crews conducted asphalt grading and paving work in Area 5.
6/3/2013 CDOT crews completed work to raise the two manhole covers in Area 5
6/9/2016 EPA OSC inspection found that the asphalt cover in a NE portion of Area 5 around the fire hydrant is in adequate and was not compacted adequately. H. Kramer contractor (GHD) /Manager was notified. GHD manager is working with the CDOT to complete repairs.
6/17 to 6/27/2016 H. Kramer contractors (GHD and RW Collins) completed the grading work and asphalt paving of Area 1 east, Area 2,4,6, and 10.
7/5-6/2016 H. Kramer contractor (RW Collins) installed traffic bollards in Areas 1 east and 2.
Crews have de-mobilized from the Site until the planned work is implemented (See Planning Section).
The following asphalt cover design was placed in Areas 1 east, 2,4,5,6,7,8,9,10. Please note that the compacted gravel layer is 6 inches thick except for Areas 1 east and 2 (where it is 3 inches). The finished (compacted) asphalt is layer is three inches thick:
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
On 9/29/2015 EPA signed an Settlement Agreement and Order on Consent For Removal Action with the PRPs for the Site: H.Kramer and Company, City of Chicago, and BNSF Railway Company.
2.1.4 Progress Metrics
Pilsen Soil Ou1 Area Name
|
Lead Contaminated Soil Excavated and Disposed
|
Disposal Facility
|
Comment
|
Area 1
|
175.3 cubic yards
|
Laraway RDF, Waste Management (Joliet, IL)
|
Excavated for grading and to meet cleanup goal.
|
Area 2
|
60.4 cubic yards
|
Laraway RDF, Waste Management (Joliet, IL)
|
Excavated for grading
|
Area 4 (Treated for TCLP Lead)
|
31.8 cubic yards
|
Laraway RDF, Waste Management (Joliet, IL)
|
|
Area 8 (Treated for TCLP Lead)
|
73.2 cubic yards
|
Laraway RDF, Waste Management (Joliet, IL)
|
|
Area 8
|
97.4 cubic yards
|
Laraway RDF, Waste Management (Joliet, IL)
|
Excavated for grading
|
Area 6 & 7
|
162 cubic yards
|
Laraway RDF, Waste Management (Joliet, IL)
|
Excavated for grading
|
Total
|
600.1 cubic yards
|
|
|
Waste Stream |
Medium |
Quantity |
Manifest # |
Treatment |
Disposal
|
Railroad ties (wood) |
|
575 feet |
|
|
disposal thru energy recovery, Staged BNSF Yard (Chicago) |
Rails (steel) |
|
1150 feet |
|
|
recycled. |
Solid waste (Garbage and Vegetation)
|
|
38.8 tons |
|
|
------------------------
Shred-Al solid waste transfer station (Chicago)
|
|
|
|
2.5.1 Safety Officer
Ramon Mendoza, EPA OSC,
Walt Pochron, GHD
2.5.2 Liaison Officer
2.5.3 Information Officer and Community Relations
Philippa Cannon, EPA (PIO support)
Clarke, Rosita, EPA (Community Relation).
Leon, Heriberto, EPA (Community Relation).
Muhtsun, Ruth (Community Relation).
|