Westwood Chemical
46 Tower Road,
Middletown, NY
Latitude: 41.4687500 Longitude: -74.3772800
|
| POLREP No.: |
6
|
Site #:
|
WN
|
| Reporting Period: |
|
D.O. #:
|
13
|
| Start Date: |
3/3/2005
|
Response Authority:
|
CERCLA
|
Mob Date: |
3/8/2005
|
Response Type:
|
Time-Critical
|
| Demob Date: |
|
NPL Status:
|
Non NPL
|
| Completion Date: |
|
Incident Category:
|
Removal Action
|
| CERCLIS ID #: |
|
Contract #
|
EP-W-04-055
|
| RCRIS ID #: |
NYD072715052
|
|
|
Offsite shipments of wastewater continued. To date a total of approximately 158,000 gallons of wastewater has been shipped for offsite disposal.Cutting-up fiberglass and poly tanks continued. To date a total of 14 tanks have been cutup.Segregation, identification and consolidation of Lab chemicals continueDismantling of known electrical equipment attached to tanks has been completed.On June 23, 2005, the RM and OSC toured the Summit Research Labs facility in Huguenot, NY to evaluate their operation in anticipation of shipping material for reuse, pending the bank's removal of the lien on the proposed material, to the Huguenot facility. The facility appeared to be operated responsibly. The tour also served as background information as to how the Westwood facility would have operated, since the two facilities manufactured antiperspirant active ingredients and flocculent agents.A compliance check of Summit Research Labs was conducted on June 29, 2005. A non-financial record review was conducted by NYS on April 06, 2004; no violations were recorded. On July 19, 2001 a CEI investigation was conducted; no violations were recorded.Two 30 cubic yard roll-offs containing debris, chiefly, cut-up tanks and process lines were shipped off site for disposal.Liquidator for the bank toured the site on June 29, 2005.Site will demobed for the July 4th break from July 1st through July 8th. Site operations will resume on July 11th. 24-Hour site security will be maintained during the demobe period.On June 21, 2005, the ERRS ceiling was raised to $1,585,000
|
|
The issuance of an RFP for the disposal of non-wastewater waste streams such as the in-process chemicals, off-spec product lines.
continue, lab chemical identification, inventorying and consolidation.
continue offsite shipment for disposal of wastewater.
continue cutting of the bulk tanks and shipping for offsite disposal.
sampling for disposal of drummed material.
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| ERRS - Cleanup Contractor |
$1,585,000.00 |
$767,000.00 |
$818,000.00 |
51.61% |
| USCG |
$40,000.00 |
$22,000.00 |
$18,000.00 |
45.00% |
|
Intramural Costs
|
| USEPA - Direct (Region, HQ) |
$100,000.00 |
$30,000.00 |
$70,000.00 |
70.00% |
| |
| Total Site Costs |
$1,725,000.00 |
$819,000.00 |
$906,000.00 |
52.52% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
response.epa.gov/westwood
POLREP #6 Last Updated 6/30/2005
|